← Bridge Power Permit Tracker

Birmingham, AL

Zoning bans gas or diesel as routine power at data centers of every size.

No gas route.

Permitted plant: No (Zoning ban)Rentals under 12 months, no air permit: No

Birmingham's zoning rules, adopted June 9, 2026, bar fossil-fuel generators as a primary, parallel or routine power source at micro, medium and hyperscale data centers. Medium sites (1–30 MW) and hyperscale sites (over 30 MW) may use only solar or fuel cells for routine on-site power. Micro sites (1 MW or less) may not run any on-site generation except emergency backup. Batteries charged from the grid or on-site solar are allowed at medium and hyperscale sites, for outages and peak demand. At medium and hyperscale sites, adding backup generation, fuel storage or electrical demand beyond the approved plan counts as a material change that needs new review. Projects already permitted before the rules were treated as exempt, per press reports.

Permitted gas generation

Fossil-fuel generators are limited to emergency backup, testing and maintenance at micro, medium and hyperscale data centers. Medium and hyperscale sites may use solar or fuel cells for routine power. Micro sites may not.

Rentals kept under 12 months

The zoning rule bans on-site generation "by any means" other than solar or fuel cells, so rented units are covered too. Source

Details

Who it covers
micro, medium and hyperscale data centers approved under the new rules, and medium or hyperscale sites that add generation, fuel storage or demand beyond their approved plan; in-house server rooms (accessory data centers) have no generation rule
Where
City of Birmingham only
Status
In force
Effective
June 9, 2026
Authority
City of Birmingham, AL (City Council, June 9, 2026)
Last checked
November 8, 2026

Sources

Check another site Need power here? Talk to us

For information only, not legal advice. Confirm with your air agency and fire marshal before you rely on it. Spot an error? Email tyler@relayenergy.us.