Where data centers
can’t run gas generators.
One answer for each place: is there a fast way for a data center to run on-site gas? We combine both routes, a permitted gas plant and rented units kept under 12 months, and link every answer to its source. Last checked November 8, 2026.
- 14
- places with no gas route: a plant is barred, and rentals are too
- 22
- more likely have none, by our reading of their rules
- 4
- states where any gas needs a months-long air permit: California, New Jersey, New Mexico, Washington (part)
- 1
- state where only rentals work, for gaps under 12 months: Texas
Is there a fast way to run gas here?
Each county combines both routes: a permitted gas plant, and rented units kept under 12 months.
Loading map…
Striped: the stricter answer covers only part of the county, such as one town, or only sites above a size. Gray means no tracked limit, not that a permit is easy: we’ve checked every state, but not yet every town. Click a county to see both answers and the rules behind them.
Can you run gas
where you are?
Pick a state and county. Nothing is sent until you ask us to follow up.
Where there’s no fast way to run gas.
Each place gets the same answer as the map, with the two answers behind it. Open a state or row for the detail and sources. Capped and not-blocked places are hidden until you turn them on.
Arizona 2 places1 no route · 1 likely no route
Marana, AZZoning limits data center generators to backup use and, from Nov 20, 2026, defines backup to exclude running while utility power is unavailable. No gas route
Permitted plant: No (Zoning ban from Nov 20, 2026)Rentals under 12 months, no air permit: No
Marana's data center code (Town Code 17-6-13) already says: "Except for generator testing or commissioning activities, generator use is limited to backup/emergency use only." Until now it did not define backup or emergency. Ordinance 2026.018, adopted Oct 20, 2026 and effective on the 31st day after adoption (Nov 20, 2026), adds a definition "for purposes of this section 17-6-13": backup/emergency use means running generators only during a genuine and unforeseen interruption of the primary supply. It expressly excludes running "as a substitute for, or supplement to, a primary electrical supply that is insufficient, inadequate, unreliable, or unavailable," including when the operator failed to secure utility power, and running for chronic or foreseeable grid shortfalls. It still allows running "during a state of emergency declared by a competent governmental authority." Data centers as a principal use need a specific plan rezoning, and the Council may waive a requirement during that rezoning (17-6-13.C).
Permitted gas generation (No: Zoning ban from Nov 20, 2026). Generators may run only for backup/emergency use, testing or commissioning. From Nov 20, 2026, backup expressly excludes running because utility power is unavailable or short, so a bridge plant is barred. A declared state of emergency is still allowed.
Rentals kept under 12 months (No). The limit is on generator use at the site, so it covers rented units too (our reading; the code doesn't mention rentals). Source
Next: Nov 20, 2026. Ordinance 2026.018 takes effect (31st day after Oct 20 adoption). Flip status to in_force and publish then.
Town of Marana, AZ (Town Council; Ord. 2024.029, Dec 2024; Ord. 2026.018, Oct 20, 2026) · Marana Town Code 17-6-13, Table 3 'Generators' (American Legal) · Marana Ordinance 2026.018 with Exhibit A (adopted Oct 20, 2026) · Checked Nov 8, 2026
Tucson, AZZoning limits generators at large data centers to backup use, run only for outages, grid instability, utility requests and testing. Likely no gas route
Permitted plant: Likely no (Emergency-only rule)Rentals under 12 months, no air permit: Likely no
Ordinance 12268, adopted Aug 5, 2026 and effective 30 days later (Sep 4, 2026), adds Unified Development Code standards for large-scale data centers: any site over 25,000 sq ft of floor area or using more than 20 MW. Either threshold triggers it, so a 5 MW site in a building over 25,000 sq ft is covered. These data centers are allowed only through a Planned Area Development or Planned Community Development rezoning. Proposed generators "must be for backup use only", and the operator must certify that generator operation "will occur only at the request of the electric utility, during grid instability or power outages or for preventive maintenance and periodic testing." Only Tier IV or natural gas / dual-fuel units are allowed where high-emitting generation is proposed. Backup must combine generators with batteries sized for 2 hours. The list of allowed operating occasions does not include running while waiting for a utility connection, so we read it to bar bridge power (our reading; the ordinance does not define "backup" or address bridge power directly). The ordinance does not say how it treats data centers that existed before it.
Permitted gas generation (Likely no: Emergency-only rule). Generators at large-scale data centers may run only at the utility's request, during grid instability or outages, or for maintenance and testing. Gas units are allowed for that backup role. We read this to rule out a 24/7 or bridge gas plant (our reading).
Rentals kept under 12 months (Likely no). The limit is on generator operation at the site, not on air permits, so we read it to cover rented units too (our reading; the ordinance doesn't mention rentals). Source
City of Tucson, AZ (Mayor and Council, Aug 5, 2026) · City of Tucson Ordinance No. 12268 (signed, Aug 5, 2026), UDC 4.9.11.D.3.d and 11.3.11.F · City of Tucson, Regulations for Large-Scale Data Centers (program page) · Checked Nov 8, 2026
Birmingham, ALZoning bans gas or diesel as routine power at data centers of every size. No gas route
Permitted plant: No (Zoning ban)Rentals under 12 months, no air permit: No
Birmingham's zoning rules, adopted June 9, 2026, bar fossil-fuel generators as a primary, parallel or routine power source at micro, medium and hyperscale data centers. Medium sites (1–30 MW) and hyperscale sites (over 30 MW) may use only solar or fuel cells for routine on-site power. Micro sites (1 MW or less) may not run any on-site generation except emergency backup. Batteries charged from the grid or on-site solar are allowed at medium and hyperscale sites, for outages and peak demand. At medium and hyperscale sites, adding backup generation, fuel storage or electrical demand beyond the approved plan counts as a material change that needs new review. Projects already permitted before the rules were treated as exempt, per press reports.
Permitted gas generation (No: Zoning ban). Fossil-fuel generators are limited to emergency backup, testing and maintenance at micro, medium and hyperscale data centers. Medium and hyperscale sites may use solar or fuel cells for routine power. Micro sites may not.
Rentals kept under 12 months (No). The zoning rule bans on-site generation "by any means" other than solar or fuel cells, so rented units are covered too. Source
City of Birmingham, AL (City Council, June 9, 2026) · City of Birmingham, data center rules · Ordinance text, ZAC2026-00001 (redline, May 27, 2026) · City release, June 9, 2026 · Checked Nov 8, 2026
Connecticut 3 places1 no route · 2 capped
Groton, CTZoning bans fossil-fuel generation at data centers except during an unforeseen loss of grid power. No gas route
Permitted plant: No (Zoning ban)Rentals under 12 months, no air permit: No
Groton's zoning, in force since July 14, 2023, bars on-site power generation using fossil fuels at data centers except during an unforeseen loss of off-site power. Data centers are allowed only by special permit in the IM and IG industrial zones, with server space capped at 12,500 square feet, at least 1,500 feet from another data center, and no evaporative cooling. Accessory data centers (the lesser of 20% of the main use or 1,000 square feet) follow the same standards without a special permit. Waiting for a utility hookup is not an 'unforeseen loss of off-site power' (our reading), so gas or diesel bridge power is barred.
Permitted gas generation (No: Zoning ban). On-site power generation using fossil fuels is barred at data centers except during an unforeseen loss of off-site power. Separately, data centers are limited to 12,500 sq ft of server space and to the IM and IG zones by special permit.
Rentals kept under 12 months (No). The rule bars 'on-site power generation using fossil fuels' with no exception for rented or temporary units, so rentals are covered too (our reading). Source
Town of Groton, CT Planning and Zoning Commission (REGA23-04, adopted June 27, 2023) · Town of Groton Zoning Regulations, Sec. 5.1-6.F Data Center (revised July 15, 2026) · Groton Planning and Zoning Commission minutes, June 27, 2023 (REGA23-04 approved 5-0, effective July 14, 2023) · The Day: Groton approves region's first data center regulations · Checked Nov 8, 2026
Greater Connecticut (Hartford, Litchfield, New London, Tolland, Windham)A 50-ton emissions line, about 20 MW of gas engines. Gas plant capped near 10–20 MW
Permitted plant: Capped (Capped near 20 MW)Rentals under 12 months, no air permit: Likely yes
In the rest of Connecticut (Hartford, Litchfield, New London, Tolland and Windham counties, except Bridgewater and New Milford), new generation that could emit 50 tons or more of NOx or VOC a year is a major source and needs nonattainment review: offsets and the strictest controls. For gas that's about 20 MW of modern engines running 24/7 (our estimate). The area is Serious under both the 2008 and 2015 ozone standards.
Permitted gas generation (Capped: Capped near 20 MW). New gas generation that could emit 50 tons a year of NOx or VOC is a major stationary source here and faces nonattainment review. That's about 20 MW of modern gas engines running 24/7 (our estimate).
Rentals kept under 12 months (Likely yes). Connecticut's permit rule exempts nonroad engines as defined in 40 CFR 1068.30 (RCSA 22a-174-3a(a)(2)(C)(ii)), so rented units kept under 12 months at one site need no DEEP permit (our reading). The state's stationary-source definition counts portable units that move site to site; ask DEEP before relying on the exemption. Source
US EPA (40 CFR 81.307 classification); CT DEEP (RCSA 22a-174-1(65)(B) and (105); 22a-174-3a nonattainment NSR) · 40 CFR 81.307, Connecticut ozone tables (eCFR, as of Nov 1, 2026) · RCSA 22a-174-1(65)(B) and (105) · Checked Nov 8, 2026
Southwest Connecticut (Fairfield, New Haven, Middlesex)A 25-ton emissions line, about 10 MW of gas engines. Gas plant capped near 10–20 MW
Permitted plant: Capped (Capped near 10 MW)Rentals under 12 months, no air permit: Likely yes
In Fairfield, New Haven and Middlesex counties, plus New Milford and Bridgewater in Litchfield County, new generation that could emit 25 tons or more of NOx or VOC a year is a major source and needs nonattainment review: offsets and the strictest controls. For gas that's about 10 MW of modern engines running 24/7 (our estimate). These towns are part of the New York-N. New Jersey-Long Island area, Severe under the 2008 ozone standard.
Permitted gas generation (Capped: Capped near 10 MW). New gas generation that could emit 25 tons a year of NOx or VOC is a major stationary source here and faces nonattainment review: offsets and the strictest controls. That's about 10 MW of modern gas engines running 24/7 (our estimate).
Rentals kept under 12 months (Likely yes). Connecticut's permit rule exempts 'non-road engine as defined in 40 CFR 1068.30' (RCSA 22a-174-3a(a)(2)(C)(ii)), so rented units kept under 12 months at one site need no DEEP permit (our reading). Caution: the state's definition of stationary source counts 'any portable emissions unit which is moved from site to site but remains stationary during operation' (22a-174-1(113)); ask DEEP before relying on the nonroad exemption. Source
Next: Jul 20, 2027. 2008 ozone attainment deadline for the NY-NJ-CT Severe area (same date as ny-nyma-ozone; not re-read this pass).
US EPA (40 CFR 81.307 classification); CT DEEP (RCSA 22a-174-1(65) and (106); 22a-174-3a nonattainment NSR) · 40 CFR 81.307, Connecticut 2008 8-hour ozone table (eCFR, as of Nov 1, 2026) · RCSA 22a-174-1(65)(A), major stationary source · RCSA 22a-174-3a(a)(2)(C), nonroad engines exempt from permit · Checked Nov 8, 2026
Georgia 12 places3 no route · 9 likely no route
Coweta County, GAZoning bars primary on-site power generation at data centers. No gas route
Permitted plant: No (Zoning ban)Rentals under 12 months, no air permit: No
Coweta County's data center ordinance says: "Notwithstanding utility grid failure, no primary onsite power generation shall be permitted." Project Sail (Prologis, nine buildings, 4.34 million sq ft, about 900 MW per press) was rezoned on April 7, 2026 under this ordinance and must follow it. The county is rewriting the ordinance under a moratorium on new applications through Dec 13, 2026.
Permitted gas generation (No: Zoning ban). No primary on-site generation. Generators are backup only and must be stationary-source, Tier 4 final units. The rule allows generation only for grid failure, which we read as not covering a wait for a new grid connection.
Rentals kept under 12 months (No). The rule bars any primary on-site generation and doesn't distinguish owned from rented units. The county administrator said in July 2026 that mobile generators aren't banned as such, but any generator must meet the ordinance (backup only, Tier 4 final). Source
Next: Dec 13, 2026. Moratorium on new data center applications ends; the ordinance is being rewritten. An Aug 2026 staff draft would have allowed on-site generation in the M district. On Oct 13 the Board told staff to drop it and keep the ban. Not adopted yet.
Coweta County, GA (Board of Commissioners, Dec 2025) · Coweta County code, data center standards (Municode) · Coweta County code, Sec. 191(12), M district (same power text; Project Sail's zoning) · Coweta Board of Commissioners minutes, April 7, 2026 · Checked Nov 8, 2026
Griffin, GAZoning bars primary on-site power generation at data centers; prime power is not a valid backup use. No gas route
Permitted plant: No (Zoning ban)Rentals under 12 months, no air permit: No
Griffin's data center rules (Ord. 26-007, adopted May 26, 2026) say: "No primary onsite power generation shall be permitted." Generators may be used only for testing and "temporary or emergency backup use", and "Use as prime power, rate curtailment, and storm avoidance shall not constitute a valid temporary or emergency backup use." Data centers are allowed only by special use permit in the Planned Industrial Development district, as Minor (up to 10,000 sq ft, no substation) or Major (10,000 to 275,000 sq ft) facilities. The applicant must show a letter from the power provider confirming capacity before a land disturbance permit. The ordinance does not say how it treats existing data centers.
Permitted gas generation (No: Zoning ban). No primary on-site power generation. Prime power is expressly not a valid backup use, so a bridge running in place of grid power is barred (our reading of 'prime power').
Rentals kept under 12 months (No). The ban reaches 'generator use' of any kind beyond testing and temporary or emergency backup, and excludes prime power. We read that as covering rented units run as prime power (our reading; the text does not name rentals). Source
City of Griffin, GA (Board of Commissioners, May 26, 2026) · City of Griffin Ord. 26-007 (Municode adopted-ordinance PDF) · Griffin UDC Sec. 503A (codified) · Checked Nov 8, 2026
Monroe County, GAZoning requires utility power for all data center operations and bans gas or diesel generators as primary power. No gas route
Permitted plant: No (Zoning ban)Rentals under 12 months, no air permit: No
Monroe County's data center standards, adopted 5-0 on April 7, 2026, say: "All operational power shall be provided by a regulated public utility." They also say: "The use of permanent or semi-permanent diesel or gas-powered generators as the primary source of power is strictly prohibited. Backup generators are permitted only for emergency and system testing purposes." Data centers are allowed only as a special use in the M-1 district, on at least 900 acres, with transmission-level (115 kV or more) service unless the County Utility Director grants an exemption. Generators must be Tier 4 final, enclosed, and tested only 10 a.m. to 4 p.m. on weekdays. The same meeting lifted the county's data center moratorium. The ordinance does not say how it treats data centers approved before it.
Permitted gas generation (No: Zoning ban). All operational power must come from a regulated public utility, and gas or diesel generators can't be the primary power source. Generators are allowed only for emergencies and testing.
Rentals kept under 12 months (No). The ban names 'permanent or semi-permanent' generators, and separately requires that all operational power come from a regulated utility. We read that as covering rented units kept for months (our reading; the text does not name rentals). Source
Monroe County, GA (Board of Commissioners, April 7, 2026) · Monroe County data center ordinance amendment (agenda text, April 2026) · Monroe County Board of Commissioners minutes, April 7, 2026 · Checked Nov 8, 2026
Athens-Clarke County, GAZoning limits data center generators to backup or emergency use (terms undefined). Likely no gas route
Permitted plant: Likely no (Emergency-only rule)Rentals under 12 months, no air permit: Likely no
Athens-Clarke County's April 7, 2026 ordinance regulates data centers as an industrial use, allowed only by special use in the Industrial (I) district. Its performance standards say: "Except for generator testing or commissioning activities, generator use is limited to backup/emergency use only." Testing is limited to 9 a.m. to 5 p.m., and data centers must use closed-loop cooling.
Permitted gas generation (Likely no: Emergency-only rule). Generators are limited to backup or emergency use. 'Emergency' and 'backup' are undefined and other on-site generation is not separately barred, so a bar on a bridge is our reading.
Rentals kept under 12 months (Likely no). The limit covers 'generator use' of any ownership, so rented units would be held to backup/emergency use too (our reading). Source
Athens-Clarke County Unified Government, GA (Mayor and Commission, Apr 7, 2026) · Athens-Clarke County Ordinance of 04-07-2026(1) (Municode adopted-ordinance PDF) · Checked Nov 8, 2026
Columbia County, GAZoning limits generators at data centers to emergency backup and testing; 'emergency' is not defined. Likely no gas route
Permitted plant: Likely no (Emergency-only rule)Rentals under 12 months, no air permit: Likely no
Columbia County, GA's data center zoning standard says: "Except for generator testing, maintenance, or commissioning activities, generator use is limited to backup /emergency use only." (Sec. 90-147(h)(6)c.b.). The ordinance does not define 'emergency' or 'backup' and does not separately bar other on-site generation. We read it as barring a generator fleet that runs 24/7 or as bridge power while a site waits for a grid connection, because that is neither emergency nor backup use (our reading). It does not meet the skill's block test on its own text. Ordinance 25-07 pages carry 'Adopted 12/02/2025'; the effective date was not stated in the pages read. 'Power supply' is a listed accessory use. Nothing on existing sites.
Permitted gas generation (Likely no: Emergency-only rule). Generator use other than testing is limited to emergency or backup use. Whether a wait for grid service counts as an emergency is not stated (our reading: it does not).
Rentals kept under 12 months (Likely no). The limit applies to all generator use on the site and does not distinguish owned from rented units. We read it as covering rented units (our reading; the text does not name them). Source
Columbia County, GA (Board of Commissioners, Dec 2, 2025; Ordinance No. 25-07) · Columbia County Ordinance No. 25-07 (Municode) · Checked Nov 8, 2026
Forsyth County, GAZoning limits generators at data centers to emergency backup and testing; 'emergency' is not defined. Likely no gas route
Permitted plant: Likely no (Emergency-only rule)Rentals under 12 months, no air permit: Likely no
Forsyth County, GA's data center zoning standard says: "With the exception of testing activities, generator use is limited to emergency backup use only." (UDC Sec. 16-4.10(E)). The ordinance does not define 'emergency' or 'backup' and does not separately bar other on-site generation. We read it as barring a generator fleet that runs 24/7 or as bridge power while a site waits for a grid connection, because that is neither emergency nor backup use (our reading). It does not meet the skill's block test on its own text. Adopted March 6, 2025 (Municode ordinance record). Testing is limited to 9 a.m. to 5 p.m. The text says nothing about existing sites.
Permitted gas generation (Likely no: Emergency-only rule). Generator use other than testing is limited to emergency or backup use. Whether a wait for grid service counts as an emergency is not stated (our reading: it does not).
Rentals kept under 12 months (Likely no). The limit applies to all generator use on the site and does not distinguish owned from rented units. We read it as covering rented units (our reading; the text does not name them). Source
Forsyth County, GA (Board of Commissioners, March 6, 2025) · Forsyth County UDC amendment of March 6, 2025 (Municode) · Checked Nov 8, 2026
Gainesville, GAZoning limits data center generators to backup or emergency use (terms undefined). Likely no gas route
Permitted plant: Likely no (Emergency-only rule)Rentals under 12 months, no air permit: Likely no
Gainesville's Unified Land Development Code, adopted Dec 16, 2025, sets data center standards in Sec. 9-8-5(a): "Except for generator testing or commissioning activities, generator use is limited to backup/emergency use only." Testing is limited to two hours on weekdays, once a month. Data centers must be at least 500 feet from residential districts and served by city water.
Permitted gas generation (Likely no: Emergency-only rule). Generators are limited to backup or emergency use. 'Emergency' and 'backup' are undefined and other on-site generation is not separately barred, so a bar on a bridge is our reading.
Rentals kept under 12 months (Likely no). The limit covers 'generator use' of any ownership, so rented units would be held to backup/emergency use too (our reading). Source
City of Gainesville, GA (City Council, ULDC adopted Dec 16, 2025) · City of Gainesville Ord. No. 2025-28 adopting the ULDC (Municode PDF) · Checked Nov 8, 2026
Paulding County, GAZoning limits generators at data centers to emergency backup and testing; 'emergency' is not defined. Likely no gas route
Permitted plant: Likely no (Emergency-only rule)Rentals under 12 months, no air permit: Likely no
Paulding County, GA's data center zoning standard says: "With the exception of testing activities, generator use is limited to emergency backup use only." (UDO Sec. 220-40.12(4)). The ordinance does not define 'emergency' or 'backup' and does not separately bar other on-site generation. We read it as barring a generator fleet that runs 24/7 or as bridge power while a site waits for a grid connection, because that is neither emergency nor backup use (our reading). It does not meet the skill's block test on its own text. Ordinance 2025-06 was signed Sept 9, 2025 (5-0) and is effective upon passage. Testing is capped at 2 hours a day, weekdays 11 a.m. to 5 p.m. The scanned redline was checked on the rendered page: the clause is underlined (added), not struck. Whether data centers are allowed outside the overlay was not checked.
Permitted gas generation (Likely no: Emergency-only rule). Generator use other than testing is limited to emergency or backup use. Whether a wait for grid service counts as an emergency is not stated (our reading: it does not).
Rentals kept under 12 months (Likely no). The limit applies to all generator use on the site and does not distinguish owned from rented units. We read it as covering rented units (our reading; the text does not name them). Source
Paulding County, GA (Board of Commissioners, Sept 9, 2025; Ordinance No. 2025-06) · Paulding County Ordinance No. 2025-06 (Municode) · Checked Nov 8, 2026
Pike County, GAZoning limits generators at data centers to emergency backup and testing; 'emergency' is not defined. Likely no gas route
Permitted plant: Likely no (Emergency-only rule)Rentals under 12 months, no air permit: Likely no
Pike County, GA's data center zoning standard says: "The testing of any generators may only be completed between the hours of 9:00 AM EST and 4:00 PM EST and the generators may only be used in the case of an emergency situation." (UDC Sec. 1403.B.5.j (M-1) and Sec. 1503.B.7 (M-2), as read into the Nov 25, 2025 minutes). The ordinance does not define 'emergency' or 'backup' and does not separately bar other on-site generation. We read it as barring a generator fleet that runs 24/7 or as bridge power while a site waits for a grid connection, because that is neither emergency nor backup use (our reading). It does not meet the skill's block test on its own text. The text comes from the Nov 25, 2025 minutes (first reading). The Dec 10, 2025 minutes record the second reading approved 5-0 with 'no proposed changes since the first reading'. The codified text was not found online.
Permitted gas generation (Likely no: Emergency-only rule). Generator use other than testing is limited to emergency or backup use. Whether a wait for grid service counts as an emergency is not stated (our reading: it does not).
Rentals kept under 12 months (Likely no). The limit applies to all generator use on the site and does not distinguish owned from rented units. We read it as covering rented units (our reading; the text does not name them). Source
Pike County, GA (Board of Commissioners, Dec 10, 2025) · Pike County BOC minutes, Nov 25, 2025 (text) and Dec 10, 2025 (adoption) · Checked Nov 8, 2026
Port Wentworth, GAZoning bars generators as primary power at data centers except in emergencies. Likely no gas route
Permitted plant: No (Zoning ban)Rentals under 12 months, no air permit: Likely no
Port Wentworth added data centers to its zoning code on Dec 18, 2025 (Ord. 2025-12-01). Data centers are permitted in the I-1 district under Sec. 7.270, which says: "Except for emergency situations, testing, or compliance purposes, external generators or power supply shall not be used for primary power." Emergency situations "shall include, but not be limited to, a power outage." The city also caps the number of data centers at one per 27,500 residents. The ordinance does not say how it treats existing sites.
Permitted gas generation (No: Zoning ban). External generators can't be used for primary power except in emergencies, testing or compliance. 'Emergency situations' is open-ended ('include, but not be limited to, a power outage'), so a grid wait is not plainly excluded; we read a months-long bridge as primary power, which the text bars.
Rentals kept under 12 months (Likely no). 'External generators or power supply' covers trailer units (our reading). The open-ended emergency definition leaves some room. Source
City of Port Wentworth, GA (Mayor and Council, Dec 18, 2025) · City of Port Wentworth Ord. 2025-12-01 (signed; Municode adopted-ordinance PDF) · Checked Nov 8, 2026
Porterdale, GAZoning limits data center generators to backup or emergency use (terms undefined). Likely no gas route
Permitted plant: Likely no (Emergency-only rule)Rentals under 12 months, no air permit: Likely no
Porterdale created a Technology Overlay District for data centers on about 270 acres at Brown Bridge Road and North Crowell Road (Apr 24, 2025). Within it: "With the exception of testing activities, generator use is limited to emergency backup use only." Testing is limited to two hours a day on weekdays.
Permitted gas generation (Likely no: Emergency-only rule). Generators are limited to backup or emergency use. 'Emergency' and 'backup' are undefined and other on-site generation is not separately barred, so a bar on a bridge is our reading.
Rentals kept under 12 months (Likely no). The limit covers 'generator use' of any ownership, so rented units would be held to backup/emergency use too (our reading). Source
City of Porterdale, GA (Mayor and Council, Apr 24, 2025) · City of Porterdale Ordinance of 04-24-2025(1) (Municode PDF) · Checked Nov 8, 2026
Rockdale County, GAZoning limits data center generators to backup or emergency use (terms undefined). Likely no gas route
Permitted plant: Likely no (Emergency-only rule)Rentals under 12 months, no air permit: Likely no
Rockdale County's rewritten Unified Development Ordinance (Ord. O-2026-06, effective Oct 1, 2026) sets standards for data centers (data management and processing uses, by special use permit). Under 'J. Generators', any generators must meet Tier 4 standards, test only 9 a.m. to 5 p.m., and: "Except for generator testing or commissioning activities, generator use is limited to backup/emergency use only." Approvals granted before the UDO stay valid.
Permitted gas generation (Likely no: Emergency-only rule). Generators are limited to backup or emergency use. 'Emergency' and 'backup' are undefined and other on-site generation is not separately barred, so a bar on a bridge is our reading.
Rentals kept under 12 months (Likely no). The limit covers 'generator use' of any ownership, so rented units would be held to backup/emergency use too (our reading). Source
Rockdale County Board of Commissioners, GA (UDO effective Oct 1, 2026) · Rockdale County Ord. O-2026-06, UDO (Municode PDF) · Checked Nov 8, 2026
Pittsfield Charter Township, MIZoning bars on-site engines and generators for continuous, prime, peaking or routine non-emergency power at data centers, from Nov 9, 2026. No gas route
Permitted plant: No (Zoning ban from Nov 9, 2026)Rentals under 12 months, no air permit: No
Pittsfield's new data center zoning section (Sec. 40-11.51) says: "On site operation of stationary engines, hydrocarbon generators, or other non-renewable energy sources for continuous, prime, peaking, or routine non-emergency energy supply is prohibited." It applies to all data centers and data processing centers (large, small and accessory) and to other 'High Resource Demand Facilities'. Generator testing is limited to weekdays 8 a.m. to 6 p.m. and 100 hours a year, and new generators must meet Tier 4 Final. A gas plant or rented gensets run as bridge power while a site waits for grid service would be continuous or prime supply, which the text bars. Data centers are a conditional use in the Industrial district only. The township board adopted the ordinance 7-0 on Oct 28, 2026; it takes effect Nov 9, 2026. The text does not say how it treats data centers built before then.
Permitted gas generation (No: Zoning ban from Nov 9, 2026). The text bars on-site engines and generators for 'continuous, prime, peaking, or routine non-emergency energy supply', so a gas plant cannot serve as primary or bridge power. Emergency use is allowed but not defined.
Rentals kept under 12 months (No). The ban covers 'hydrocarbon generators' as well as stationary engines, without regard to ownership or how long they stay, so we read it as covering rented gensets (our reading; the text does not name rentals). Michigan's air rules on rentals are unclear (pass 1). Source
Next: Nov 9, 2026. ZOA #26-236 takes effect (township page). Flip status to in_force. Get the signed, published ordinance and compare it with the Oct 28 second-reading text.
Pittsfield Charter Township, MI (Board of Trustees, ZOA #26-236, adopted at second reading Oct 28, 2026) · Pittsfield ZOA #26-236, Sec. 40-11.51, second-reading text (Board of Trustees packet, Oct 28, 2026, item 10.2) · Pittsfield Charter Township, Data Center Ordinance page · Checked Nov 8, 2026
NashvilleZoning bans on-site fossil power except emergencies and testing. No gas route
Permitted plant: No (Zoning ban)Rentals under 12 months, no air permit: No
In Nashville and Davidson County, a data center may not run on-site diesel or gas generation as a primary, parallel or routine power source. Generators may run only for testing, commissioning, and defined emergencies (an NES outage, an NES request during grid strain, or a TVA EEA level 2 or 3 alert). Units must meet EPA Tier 4.
Permitted gas generation (No: Zoning ban). On-site generation by any means except solar, wind, geothermal and waste heat is banned as a primary, parallel or routine power source. Data centers operating before July 31, 2026 may argue they're protected as an existing use; no court has decided this. Under the new zoning, adding square footage or capacity needs a new permit. A developer's federal lawsuit against the rules was dismissed on Oct 6, 2026, mostly without prejudice, so parts of it could be refiled.
Rentals kept under 12 months (No). The zoning ban covers on-site generation 'by any means' as primary power. We read that as covering rented units too; the ordinance doesn't name them. Source
Next: Dec 1, 2026. Companion moratorium on new data center permits ends; the gas ban stays.
Metropolitan Council of Nashville and Davidson County, Ordinance BL2026-1391 (Title 17 zoning code), as amended on third reading · BL2026-1391 legislation detail and history (Legistar) · Amendment H to BL2026-1391 (Capp), adopted July 21, 2026 · Legistar action detail, July 21, 2026 (Amendment H adopted; final vote 36-0) · Checked Nov 8, 2026
New Jersey 2 places1 no route · 1 permit only
Bridgewater Township, NJZoning limits every data center generator to outages and testing. No gas route
Permitted plant: No (Zoning ban)Rentals under 12 months, no air permit: No
Bridgewater's land use code, effective Sep 23, 2026, says any generator at a data center may run only during an emergency or for testing and maintenance, and defines an emergency as loss of primary power from an outage beyond the data center's control. Only natural gas generators are allowed, since no fuel may be stored on the property, and battery energy storage systems are barred. The rules apply to any data center not already existing in its current condition when the ordinance passed, whether or not a zone or redevelopment plan permits the use.
Also applies here: New Jersey, which sets this place's answer together with this rule.
Permitted gas generation (No: Zoning ban). Any generator may run only during a utility outage beyond the data center's control, or for limited testing. Section 1.a lists 'energy generation systems' as an accessory use, which we read as covering on-site renewables (an on-site renewable source is required), not gas engines run as primary power.
Rentals kept under 12 months (No). The emergency-only rule covers 'any generator', and no fuel may be stored on the property. Source
Township of Bridgewater, Somerset County, NJ (Council, adopted Sep 3, 2026) · Bridgewater Ordinance 26-15, Section 126-341.6.C.1.c.iii · Bridgewater Ordinance 26-15, Section 126-341.6.A · Patch, Sep 8, 2026 (adoption) · Checked Nov 8, 2026
New JerseyAny non-emergency engine kept over 30 days needs a state permit; 25-ton NOx line statewide. Only with a months-long air permit
Permitted plant: Capped (Permit; 25-ton line)Rentals under 12 months, no air permit: No
In New Jersey, a reciprocating engine that stays more than 30 days at one site is a stationary engine, and any stationary engine of 37 kW or more that generates electricity, other than an emergency generator, needs a preconstruction permit and operating certificate before it is installed. So a rented gas or diesel fleet run as bridge power needs the same permit as a permanent plant. A site that could emit 25 tons a year of NOx or VOC faces LAER and emission offsets, and every county in the state is in an ozone nonattainment area. That is about 10 MW of modern gas engines running 24/7 (our estimate). NJDEP fined DataOne in Vineland ,072,000 on Sep 22, 2026 for running 62 unpermitted 1,982 kW gas engines as stationary engines.
Permitted gas generation (Capped: Permit; 25-ton line). Non-emergency engines of 37 kW or more need a preconstruction permit. At 25 tpy of NOx or VOC potential, the site needs LAER and emission offsets: about 10 MW of gas engines running 24/7 (our estimate, 6-18 MW).
Rentals kept under 12 months (No). Any engine kept more than 30 days at one site counts as stationary and needs the same permit. The 'construction engine' exclusion (a mobile generator used until power lines arrive, 12 months or less) is untested for a running data center; we read it as construction power only. Source
NJDEP, N.J.A.C. 7:27-8 (permits and certificates) and 7:27-18 (Emission Offset Rule) · N.J.A.C. 7:27-8 (NJDEP courtesy copy) · N.J.A.C. 7:27-8.2(c)21 (significant sources needing a permit) · N.J.A.C. 7:27-18.2 (Emission Offset Rule applicability) · Checked Nov 8, 2026
OregonAir permits for new or expanded data centers paused to July 1, 2027. No gas route
Permitted plant: No (Through Jul 1, 2027)Rentals under 12 months, no air permit: No
At the Governor's request (Oct 9, 2026 letter), Oregon DEQ has paused air and water permits for new or expanded data centers until July 1, 2027. DEQ told reporters it will end the pause sooner if the Governor says so, and that it is still working on applications up to a draft permit, then holding them. So no permit for a new or expanded data center can be finalized before then.
Permitted gas generation (No: Through Jul 1, 2027). Running gas 24/7 at a data center would almost certainly push it past its permitted emission limit, and going past that limit needs a modified DEQ permit. At the Governor's request DEQ has paused permits for new or expanded data centers.
Rentals kept under 12 months (No). Oregon requires a DEQ air permit for combustion power generation from any unit of 500 kW or more that isn't used only for emergencies, with no exemption for portable or nonroad units. A fleet of smaller units can still need a permit once the site's emissions pass its permit limit or 10 tons a year. For a new or expanded data center, that permit falls under the pause. A small temporary unit inside the site's existing emission limit may avoid a new permit, but DEQ hasn't said whether bridge power qualifies. Source
Next: Dec 31, 2026. Governor's data center advisory committee recommendations expected by the end of the year
Governor of Oregon (Tina Kotek), letter to DEQ Director Leah Feldon; implemented by Oregon DEQ · Gov. Kotek letter to DEQ Director Leah Feldon, Oct 9, 2026 (copy hosted by OPB) · Oregon DEQ, Data Center Air Quality Permitting, presentation to Governor's Data Center Advisory Committee, Jul 31, 2026 · OPB, Oct 29, 2026 (DEQ spokesperson on implementation) · Checked Nov 8, 2026
Pennsylvania 4 places2 no route · 1 likely no route · 1 capped
Blakely Borough, PAZoning bars on-site generation at data centers; generators only as backup to the borough's own utility. No gas route
Permitted plant: No (Zoning ban)Rentals under 12 months, no air permit: No
Blakely's zoning allows data centers only as a conditional use in the DT Overlay zone, and Section 775.G says: "No on-site electrical generation is allowed." Backup generation is allowed. The borough-wide definition of a generator adds that generators "shall not be used for primary power only as a backup to the borough electrical distribution system." A data center must take its power from the Blakely Borough Electric Light Company, and the applicant must provide a certification from the regional transmission organization that sufficient power is available. Generators may not be used for peak shaving or demand response. "Backup" is not defined, but running a gas fleet while waiting for the borough to serve the load would be primary power, which the text bars (our reading).
Permitted gas generation (No: Zoning ban). 'No on-site electrical generation is allowed' at data centers (Sec. 775.G), and generators may serve 'only as a backup to the borough electrical distribution system' (definition, Sec. 302). Power must come from the Blakely Borough Electric Light Company (775.H).
Rentals kept under 12 months (No). The generator definition expressly includes portable units, and the data center section bars on-site generation outright. Source
Blakely Borough Council, Lackawanna County, PA (data center rules first adopted Nov 17, 2025 per press; zoning ordinance with amendments readopted Sep 21, 2026) · Blakely Borough Zoning Ordinance (Ord. 8 of 2026, adopted Sep 21, 2026), Sec. 775.G · Same, Sec. 302 definition of 'Generator (Fuel or Battery Powered)' · Same, Sec. 775.H and Sec. 111 · Checked Nov 8, 2026
Dallas Township, PAZoning limits on-site generation to utility outages, 30 days in any 90. No gas route
Permitted plant: No (Zoning limit)Rentals under 12 months, no air permit: No
Dallas Township's zoning, amended Jul 28, 2026, says a data center's primary power will come from a public utility. On-site generation may run only when that primary source is unavailable, and no on-site generation may continue longer than 30 days in total in any 90-day period. Data centers are allowed only as a conditional use in the I-1 General Industrial District.
Permitted gas generation (No: Zoning limit). Primary power must come from a public utility. On-site generation runs only when that source is unavailable, and no more than 30 days in any 90.
Rentals kept under 12 months (No). The 30-in-90-day limit applies to any on-site power generation, so rentals are covered (our reading). Source
Dallas Township Board of Supervisors, Luzerne County, PA (adopted Jul 28, 2026) · Dallas Township Ordinance No. 3 of 2026, final proposed text dated Jul 20, 2026, Section G.1 · Dallas Township special meeting minutes, Jul 28, 2026 (scanned) · Times Leader, Jul 28, 2026 · Checked Nov 8, 2026
Londonderry Township (Dauphin County), PAZoning bars generators from serving as a data center's primary power except in an emergency. Likely no gas route
Permitted plant: Likely no (Emergency-only rule)Rentals under 12 months, no air permit: Likely no
Londonderry Township's Data Center Overlay, enacted Feb 11, 2026 and effective five days later, makes data centers a conditional use in the overlay and sets general requirements in Section 1404. Section 1404.J.3 says: "Auxiliary power systems, including generators, shall not act as the primary power source for a Data Center in any non-emergency situation." "Emergency" is not defined. A gas fleet run while the site waits for utility service would be primary power in a non-emergency situation, so we read the rule to bar bridge power (our reading). An applicant inside the overlay may choose to submit under the underlying district's rules instead (Sec. 1402.1); whether those districts allow data centers at all was not checked.
Permitted gas generation (Likely no: Emergency-only rule). Generators may not act as a data center's primary power in any non-emergency situation (Sec. 1404.J.3). 'Emergency' is undefined, so a bar on bridging is our reading.
Rentals kept under 12 months (Likely no). Covers any generator acting as primary power, rented or owned (our reading). Source
Londonderry Township Board of Supervisors, Dauphin County, PA (enacted Feb 11, 2026) · Londonderry Township Ordinance 2026-03, Sec. 1404.J.3 (signed copy hosted on Conewago Township's site) · Same, Sec. 7 and signature block · Same, Sec. 1402.1 · Checked Nov 8, 2026
Philadelphia area, PAA 25-ton NOx/VOC line in the five Philadelphia counties, about 10 MW of gas engines. Gas plant capped near 10–20 MW
Permitted plant: Capped (Capped near 10 MW)Rentals under 12 months, no air permit: Unknown
In Bucks, Chester, Delaware, Montgomery and Philadelphia counties, Pennsylvania's nonattainment review applies once aggregated NOx or VOC increases exceed 25 tons a year, with offsets and the strictest controls. For gas that's about 10 MW of modern engines running 24/7 (our estimate). The area is Serious for the 2015 ozone standard, where the federal line would be 50 tons, but Pennsylvania's rule names these five counties at 25.
Permitted gas generation (Capped: Capped near 10 MW). Once aggregated NOx or VOC increases exceed 25 tons a year, nonattainment review applies: offsets at 1.2:1 and LAER (or BACT if offset internally). About 10 MW of gas engines running 24/7 (our estimate, 6-18 MW). Applying the 25-ton line to a brand-new facility is our reading of 127.203(b)(1).
Rentals kept under 12 months (Unknown). Diesel nonroad rentals can use DEP's GP-11 general permit (compression-ignition only). Gas rentals have no general permit; they need a plan approval unless all exempt engines at the site stay under 6.6 tons of NOx a year (DEP exemption category 6). Our reading. Source
PA DEP (25 Pa. Code 127.203(b)); Philadelphia Air Management Services administers permits in Philadelphia; US EPA (classification) · 25 Pa. Code 127.203 · 25 Pa. Code 127.210 (offset ratios) · EPA Green Book, 8-Hour Ozone (2015) (data current Oct 31, 2026) · Checked Nov 8, 2026
Virginia 5 places2 no route · 3 likely no route
Amherst County, VAZoning bars running data center generators except in power outages, testing and maintenance, and bars trailer-housed generators for normal operation. No gas route
Permitted plant: No (Zoning limit)Rentals under 12 months, no air permit: No
Amherst County's zoning code says: "Generators for a data center must not be operated other than during emergency power outages and for testing and maintenance." Testing and maintenance may run only Monday to Friday, 10 a.m. to 4 p.m., and no more than four hours a month. It also says: "No temporary structures or vehicles that house generators or generating equipment shall be allowed as a means of normal operation for the data center facility." Section 927 applies to every data center as defined in Sec. 302, except server rooms inside a building that serve another use and have no exterior generators. A gas or diesel fleet run as bridge or primary power while a site waits for grid service is not running during a power outage, so we read the rule as barring it (our reading). The code does not address fuel cells. How it treats data centers approved before Aug 18, 2026 was not read.
Permitted gas generation (No: Zoning limit). Generators for a data center may run only during emergency power outages and for weekday daytime testing and maintenance (at most four hours a month). A gas plant made of generators cannot serve as primary or bridge power (our reading of 'emergency power outages').
Rentals kept under 12 months (No). Sec. 927.04.3(g) bars 'temporary structures or vehicles that house generators or generating equipment' as a means of normal operation, which covers trailer-mounted rentals in normal operation. The outage-only limit in (e) covers all 'generators for a data center' regardless of ownership (our reading). State air rules do not reach nonroad rentals kept 12 months or less (9VAC5-80-1110). Source
Amherst County, VA (Board of Supervisors, Ord. No. 2026-6, Aug 18, 2026) · Amherst County Zoning Ordinance Sec. 927.04.3(e), Data Centers (Municode, codified through Ord. 2026-6) · Amherst County Zoning Ordinance Sec. 927.04.3(g) · Checked Nov 8, 2026
Henrico County, VAZoning bars running data center generators except in power outages, testing and maintenance. No gas route
Permitted plant: No (Zoning limit)Rentals under 12 months, no air permit: No
Henrico County's zoning code says: "Generators for a data center must not be operated other than during emergency power outages and for testing and maintenance." Testing and maintenance may run only Monday to Friday, 10 a.m. to 4 p.m. The standard applies to data centers as a principal use and, by cross-reference, to accessory data centers serving an office or industrial use. A gas or diesel generator fleet run as bridge or primary power while a site waits for grid service is not running during a power outage, so we read the rule as barring it (our reading). The code does not address fuel cells or other non-generator sources. How the rule treats data centers built before June 10, 2025 is not stated in the sections read.
Permitted gas generation (No: Zoning limit). Generators for a data center may run only during emergency power outages and for weekday daytime testing and maintenance. A permanent gas plant made of generators cannot serve as primary or bridge power (our reading of 'emergency power outages').
Rentals kept under 12 months (No). The standard covers any 'generators for a data center' without regard to ownership or how long they stay, so we read it as covering rented units too (our reading; the text does not name rentals). State air rules do not reach nonroad rentals kept 12 months or less (9VAC5-80-1110). Source
Henrico County, VA (Board of Supervisors, Ord. No. 1342, June 10, 2025) · Henrico County Code Sec. 24-4328.B, Data Centers (Municode, version Sep 30, 2026) · Henrico County Code Sec. 24-4438, Accessory Data Center · Checked Nov 8, 2026
Goochland County, VA (Technology Overlay District)In the technology overlay, generators near homes may run only for testing and emergencies, defined as outages beyond the operator's control. Likely no gas route
Permitted plant: Likely no (Emergency-only rule)Rentals under 12 months, no air permit: Likely no
Goochland County's technology overlay district (TOD) standards say: "Generators cannot be operated other than for testing and during emergencies." They define emergencies as times when, "due to circumstances beyond the facility operator's control, the principal energy source to the facility is temporarily unavailable", when the utility directs generator use to protect the grid, or at the direction of emergency services. The limit sits in the noise standards, which apply "for conceptual master plans adjacent to either residentially-zoned property or mixed-use development with residential uses". The TOD standards reach data centers that are permitted only through the TOD, that take technology-zone incentives, or that are by right but adjacent to homes (Sec. 15-448.B). Data centers are by right in M-1 elsewhere with no generator-use limit. So the bar covers only part of the county. Whether a wait for first grid service counts as the principal energy source being "temporarily unavailable" is not settled by the text; we read a planned bridge as not an emergency (our reading).
Permitted gas generation (Likely no: Emergency-only rule). Where the TOD noise standards apply, generators may run only for testing and defined emergencies (outages beyond the operator's control, utility direction, emergency services). The definition could be argued to cover a grid-connection delay, so the bar on a bridge is our reading.
Rentals kept under 12 months (Likely no). The limit covers all generators at a covered site, so we read it as covering rentals there (our reading). Outside covered sites, no zoning limit was found. Source
Goochland County, VA (Board of Supervisors, Ord. No. 6471, Nov 6, 2025) · Goochland County Code Sec. 15-449.A(1)d(i), TOD design standards · Goochland County Code Sec. 15-448.B(3) · Checked Nov 8, 2026
Stafford County, VAZoning limits data center generators to backup and emergency use; 'emergency' is not defined. Likely no gas route
Permitted plant: Likely no (Emergency-only rule)Rentals under 12 months, no air permit: Likely no
Stafford County's zoning code, under 'Special provisions applicable to data centers', says: "Except for generator testing or commissioning activities, generator use shall be limited to backup and emergency use only." Before a rezoning is approved, the developer must show documentation from the electric provider on the load, availability and timing of power. Testing may run only on weekdays, 9 a.m. to 5 p.m., not on holidays. Data centers are a by-right use in M-2. A bridge plant made of generators that runs while a site waits for the grid is not backup power, so we read the rule as barring it (our reading). The text does not define 'emergency' and does not mention fuel cells or other non-generator sources.
Permitted gas generation (Likely no: Emergency-only rule). Generator use at data centers is limited to backup, emergency, testing and commissioning, so a permanent gas plant made of generators cannot be primary or bridge power (our reading).
Rentals kept under 12 months (Likely no). The limit covers all 'generator use', so we read it as covering rented units (our reading; the text does not name rentals). Source
Stafford County, VA (Board of Supervisors; added by an ordinance on or before Dec 2, 2025, not confirmed which) · Stafford County Code Sec. 28-39(q), Special provisions applicable to data centers (Municode) · Checked Nov 8, 2026
York County, VAZoning limits data center generators to backup and emergency use, plus testing and commissioning. Likely no gas route
Permitted plant: Likely no (Emergency-only rule)Rentals under 12 months, no air permit: Likely no
York County's data center standards say: "Except for generator testing or commissioning activities, generator use is limited to backup/emergency use only." Testing may run one generator at a time, weekdays 5 to 8 p.m. Data centers need a special use permit, and the application must include a letter from the electric utility on the energy source and the load at each phase. The code does not define "backup" or "emergency", so whether it bars a gas bridge while a site waits for grid service is our reading: a fleet run as the site's main supply is not backup (our reading). Same wording as Stafford County.
Permitted gas generation (Likely no: Emergency-only rule). Generator use is limited to backup and emergency use, testing and commissioning. 'Emergency' is undefined, so a bar on bridge or primary gas generation is our reading.
Rentals kept under 12 months (Likely no). The limit covers all 'generator use' at a data center, so we read it as covering rented units (our reading; the text does not name rentals). Source
York County, VA (Board of Supervisors, Ord. No. 26-12, May 19, 2026) · York County Code Sec. 24.1-489.1(f)(5), Standards for data centers (Municode, codified through Ord. 26-12) · York County Ord. No. 26-12 (May 19, 2026), ZT-216-25 · Checked Nov 8, 2026
Edgefield County, SCZoning limits every generator at a data center to backup or emergency use. Likely no gas route
Permitted plant: Likely no (Emergency-only rule)Rentals under 12 months, no air permit: Likely no
Edgefield County's data center rules, adopted July 7, 2026, say: "Except for generator testing or commissioning activities, generator use is limited to backup/emergency use only." The rule covers "any generators on the property" of a data center of any size. Data centers, data center campuses and crypto mining centers are allowed only in the county industrial park at Generac Way, Trenton, at least 1,000 feet from homes. Generators must meet Tier 4 standards and may be tested at most 10 hours a month, 9 a.m. to 5 p.m. The ordinance does not say how it treats sites approved before it.
Permitted gas generation (Likely no: Emergency-only rule). Generators at a data center may run only for backup or emergency, plus testing and commissioning. 'Backup' is not defined; we read it to exclude bridging while waiting for grid service. Whether this bars a bridge while waiting for the grid is our reading; the rule doesn't say.
Rentals kept under 12 months (Likely no). The limit applies to "any generators on the property", so rented units are covered (our reading). Source
Edgefield County, SC (County Council, July 7, 2026) · Edgefield County Ordinance 25-26-009 (signed and recorded, Instrument 2026-2808) · February 2026 draft (same generator text) · Checked Nov 8, 2026
Florida 5 places5 likely no route
Hernando County, FLPauses county or city approvals to build or expand data centers, generators included. Likely no gas route
Permitted plant: No (Moratorium to Jun 23, 2027)Rentals under 12 months, no air permit: Likely no
Hernando County paused, for 365 days from its effective date, the issuance of development orders or permits, including building permits, "that allows for the initiation, construction, expansion, or modification of existing or new data centers" in unincorporated areas. Data center has the state-law meaning, which includes large-scale data centers. Existing lawfully built development is not affected, and applications received before the effective date continue to be processed. The pause can be extended once by up to 120 days.
Permitted gas generation (No: Moratorium to Jun 23, 2027). Local approvals to establish or expand a covered data center are paused. A generator addition needing a local permit is paused (our reading). It pauses new data centers too, and likely battery additions at existing ones (our reading).
Rentals kept under 12 months (Likely no). Rented units need no Florida air permit, but a local building, electrical or site approval for them at a covered data center would be paused (our reading). Source
Next: Jun 23, 2027. Moratorium ends unless extended or replaced by new rules
Hernando County Board of County Commissioners, FL (June 23, 2026) · Hernando County Code App. A, Art. V, Sec. 11 (Ord. 2026-15, codified) · Checked Nov 8, 2026
Leon County, FL (50 MW+)Pauses county approvals to build, expand or operate sites of 50 MW or more, generators included. Likely no gas route
Permitted plant: No (Moratorium to Apr 13, 2028)Rentals under 12 months, no air permit: Likely no
Leon County paused for 18 months the acceptance, review or approval of rezonings, conditional uses, development permits, site plans, building permits and other approvals "for the construction, expansion, or operation of facilities serving large load customers, including large-scale data centers" in unincorporated areas. Large load means an anticipated monthly peak of 50 MW or more at one location. Properties with documented damage from Hurricanes Debby or Helene are exempt.
Permitted gas generation (No: Moratorium to Apr 13, 2028). Local approvals to establish or expand a covered data center are paused. A generator addition needing a local permit is paused (our reading). It pauses new data centers too, and likely battery additions at existing ones (our reading).
Rentals kept under 12 months (Likely no). Rented units need no Florida air permit, but a local building, electrical or site approval for them at a covered data center would be paused (our reading). Source
Next: Apr 13, 2028. Moratorium ends unless extended or replaced by new rules
Leon County Board of County Commissioners, FL (Oct 13, 2026) · Leon County Ord. 2026-15 (Municode PDF; posted copy number blank) · Checked Nov 8, 2026
Levy County, FLPauses county or city approvals to build or expand data centers, generators included. Likely no gas route
Permitted plant: No (Moratorium to Oct 6, 2027)Rentals under 12 months, no air permit: Likely no
Levy County paused, for 12 months from its effective date, the acceptance, review and approval of development permits and development orders for data center facilities in unincorporated areas. The definition says such facilities may include power generators. Existing permits and orders stay valid.
Permitted gas generation (No: Moratorium to Oct 6, 2027). Local approvals to establish or expand a covered data center are paused. A generator addition needing a local permit is paused (our reading). It pauses new data centers too, and likely battery additions at existing ones (our reading).
Rentals kept under 12 months (Likely no). Rented units need no Florida air permit, but a local building, electrical or site approval for them at a covered data center would be paused (our reading). Source
Next: Oct 6, 2027. Moratorium ends unless extended or replaced by new rules
Levy County Board of County Commissioners, FL (Oct 6, 2026) · Levy County Ord. 2026-05 (signed; Municode PDF) · Checked Nov 8, 2026
Nassau County, FLPauses all county approvals for building, expanding or operating data centers, generators included. Likely no gas route
Permitted plant: No (Moratorium to about Jun 8, 2027)Rentals under 12 months, no air permit: Unknown
Nassau County paused the acceptance, review or approval of rezonings, conditional uses, development permits, site plans, building permits and other development approvals "for the construction, expansion, or operation of Data Center Facilities" in unincorporated areas, for 12 months or until new rules take effect. The definition says such facilities "may include air handlers, power generators". A county permit for a generator at a data center is therefore paused (our reading).
Permitted gas generation (No: Moratorium to about Jun 8, 2027). County approvals for data center construction, expansion or operation are paused. It pauses new data centers too, and likely battery additions at existing ones (our reading).
Rentals kept under 12 months (Unknown). Rented units need no state air permit, but a county building or site permit for them at a data center would be paused (our reading).
Next: Jun 8, 2027. Moratorium ends 12 months after it took effect (approximate; it takes effect on filing with the Secretary of State), unless new rules take effect first
Nassau County Board of County Commissioners, FL (reported adopted June 8, 2026) · Nassau County, Data Centers page · Ordinance 2026-044, first-reading draft · News4Jax, June 9, 2026 · Checked Nov 8, 2026
Zephyrhills, FLPauses county or city approvals to build or expand data centers, generators included. Likely no gas route
Permitted plant: No (Moratorium to Jun 22, 2027)Rentals under 12 months, no air permit: Likely no
Zephyrhills paused for one year, from June 22, 2026, the acceptance, review and issuance of any city approval for the establishment, expansion or intensification of any data center, data center facility, large-scale data center or large load customer facility. 'Expansion or intensification' expressly includes any change that increases generator capacity, battery storage or fuel storage. The data center definition has no size floor.
Permitted gas generation (No: Moratorium to Jun 22, 2027). Local approvals to establish or expand a covered data center are paused. A generator addition needing a local permit is paused (our reading). It expressly pauses added battery storage as well.
Rentals kept under 12 months (Likely no). Rented units need no Florida air permit, but a local building, electrical or site approval for them at a covered data center would be paused (our reading). Source
Next: Jun 22, 2027. Moratorium ends unless extended or replaced by new rules
City of Zephyrhills, FL (City Council, June 22, 2026) · City of Zephyrhills Ord. 1523-26 (signed; Municode PDF) · Checked Nov 8, 2026
Monticello, MNData center zoning lets backup generators run only during a power outage; utility curtailment is not an outage. Likely no gas route
Permitted plant: Likely no (Outage-only backup rule)Rentals under 12 months, no air permit: Likely no
Monticello requires every data center to be built in a Data Center PUD district (DCPUD). Its standards say: "Back-up power generators within the DCPUD may only be used for back-up electrical supply during a power outage. Curtailment of power supply or voluntary shutdown of power is not considered a power outage." Testing is limited to weekdays 8 a.m. to 5 p.m. To be rezoned, a project must show it 'will be adequately served with electricity supplies for the specified data center demands from the local electric power supplier'. The ordinance lists 'outdoor generators' as accessory support facilities and does not expressly bar a primary generation plant, so we read the outage-only limit, the utility-supply showing and the definition (which names 'back-up power generators') together as ruling out a gas bridge (our reading). Deviations need a variance.
Permitted gas generation (Likely no: Outage-only backup rule). Backup generators may run only during a power outage, and curtailment is not an outage. A wait for first grid service is not an outage, and rezoning requires utility supply (our reading). The text does not expressly name or bar prime generators.
Rentals kept under 12 months (Likely no). The outage-only limit is on generator use in the district, so we read it as covering rented units (our reading; the text does not name rentals). Separately, the DCPUD bars 'semi-trailer containers' used as storage; whether that reaches trailer gensets is doubtful.
City of Monticello, MN (City Council, Ordinance 865, Apr 27, 2026) · Monticello Ordinance 865, Data Center PUD (adopted Apr 27, 2026) · Monticello Ordinance 865, rezoning criteria · Checked Nov 8, 2026
New York 2 places1 likely no route · 1 capped
Sites of 50 MW or moreDEC permits held for building or expanding data centers of 50 MW+. Likely no gas route
Permitted plant: No (DEC permits on hold)Rentals under 12 months, no air permit: Unknown
New York's environmental agency is holding any discretionary permit for building or expanding a data center that uses or can use 50 MW or more, for applications not complete by July 14, 2026, until a statewide environmental study the Governor says will take up to a year. Air permits aren't named; we read them as covered.
Permitted gas generation (No: DEC permits on hold). The order holds discretionary DEC permits for building or expanding data centers of 50 MW or more, and lets DEC ask whether an application involves a data center's operation. A gas plant for a new or expanding site is likely held. One added at a site that is not growing is arguably outside the hold (our reading).
Rentals kept under 12 months (Unknown). The rules don't say whether rented units need a state air permit. If they do, a fleet that stays under half the major-source lines can use a registration: 12.5 tons of NOx a year in the NYC area, or 50 tons of NOx and 25 tons of VOC upstate. Registrations are ministerial, so the hold should not reach them. A bigger fleet needs a state facility or Title V permit, which the hold likely catches at 50 MW+ sites being built or expanded. Source
Next: Dec 31, 2026. S10642 (A11560) passed both houses in June but has not been sent to the Governor. It dies if not sent before the session ends Dec 31. Once sent, she has 10 days, Sundays excepted, to sign or veto, or it becomes law without her signature.
Governor of New York (Kathy Hochul), Executive Order No. 62; implemented by NYSDEC · Executive Order No. 62, 'Establishing a Temporary Moratorium on Data Centers in New York While the State Develops Higher Standards for Data Center Development and Benefits Blueprint to Support Localities', Jul 14, 2026 · Governor of New York, Executive Orders index · Governor's press release, Sep 15, 2026 (Community Investment Framework) · Checked Nov 8, 2026
New York City areaA 25-ton emissions line, about 10 MW of gas engines. Gas plant capped near 10–20 MW
Permitted plant: Capped (Capped near 10 MW)Rentals under 12 months, no air permit: Unknown
In NYC, Long Island, Westchester and Rockland, new generation that could emit 25 tons or more of NOx or VOC a year triggers major-source review: emission offsets and the strictest controls. For gas that's about 10 MW of modern engines running 24/7 (our estimate).
Permitted gas generation (Capped: Capped near 10 MW). New gas generation that could emit 25 tons a year of NOx, or 25 tons of VOC, faces major-source review: offsets and the strictest controls. That's about 10 MW of modern gas engines running 24/7 (our estimate; roughly 6–18 MW depending on the engine). At sites under 25 tons a year of NOx potential, engines of 200 hp or more run in place of utility power must also meet New York's Part 222 NOx limit (1.0 g/bhp-hr for gas). Engines at a site with no utility service are outside Part 222.
Rentals kept under 12 months (Unknown). If rented units need a state permit (the rules are unclear), New York's small-engine exemption stops at 200 bhp per engine in the New York City area and seven Orange County towns, and applies only at sites without a Title V permit. A registration covers only about 1 MW of uncontrolled gas engines there (our estimate). A larger fleet needs a state facility permit, or a Title V permit once potential emissions reach 25 tons a year. Inside the city, portable generators of 40 kW or more also need a DEP registration. Source
Next: Jul 20, 2027. Attainment deadline. Severe areas that miss it are not moved up automatically. Instead, large sources pay Clean Air Act Section 185 fees and New York must write a new plan. The 10-ton Extreme line would apply only if New York asks EPA to reclassify the area.
US EPA (designation/classification); NYSDEC (6 NYCRR Part 231 nonattainment NSR; Part 222 distributed generation) · NYSDEC SIP revision incorporating 6 NYCRR Part 222, Distributed Generation Sources · Clean Air Act §182(e), Extreme areas (42 U.S.C. 7511a) · EPA Green Book, 8-Hour Ozone (2008) by classification (data current Oct 31, 2026) · Checked Nov 8, 2026
California 8 places8 permit only
CaliforniaRentals can't supply primary power; a permitted gas plant needs a district permit and, past a site-wide line, offsets. Only with a months-long air permit
Permitted plant: Possible (District permit, with offsets)Rentals under 12 months, no air permit: No
California's statewide portable equipment registration (PERP) isn't valid for supplying a site's primary power, except utility outages, maintenance, a failed backup generator (up to 180 days) and electrical-upgrade work (90 days, or longer if the district agrees in writing). So rented units need a district permit like any prime engine. Each air district permits prime gas engines with strict NOx limits and requires offsets once the whole site passes its line, from about 2 MW of gas in the South Coast to about 12 MW in San Diego, Imperial and the High Desert (our estimates).
Permitted gas generation (Possible: District permit, with offsets). No statewide ban. A new prime gas engine needs an air district permit with best available controls, and offsets once the site passes the district's line (about 2–12 MW of gas, our estimates).
Rentals kept under 12 months (No). PERP registration isn't valid for supplying a site's primary power. The only exceptions are utility outages, maintenance, a failed backup generator (up to 180 days), and electrical-upgrade work (90 days, or longer if the district agrees in writing). Source
California Air Resources Board (PERP); local air districts · CARB Statewide Portable Equipment Registration regulation, 13 CCR 2453(m)(4)(E) · Checked Nov 8, 2026
Bay AreaBackup units can't be the bridge; new prime gas engines need offsets once the whole site passes 10 tons of NOx a year (about 5 MW of gas on an otherwise clean site). Only with a months-long air permit
Permitted plant: Possible (With offsets past 10 tons NOx/yr site-wide)Rentals under 12 months, no air permit: No
Generators permitted as emergency backup at Bay Area data centers can only run for real, unforeseeable outages plus 50 hours a year of testing, so they cannot carry a site while it waits for power; a new engine meant to run as prime power needs a separate, stricter permit with offsets once the site passes 10 tons of NOx a year.
Also applies here: California, which sets this place's answer together with this rule.
Permitted gas generation (Possible: With offsets past 10 tons NOx/yr site-wide). Backup generators can't run as bridge power. A new prime gas engine can be permitted with best available controls, plus a health risk assessment if its toxic emissions pass district trigger levels. Once the whole site's potential NOx passes 10 tons a year (about 5 MW of gas on an otherwise clean site), the increase must be offset. Up to 35 tons the district supplies offsets from its small-facility bank if the bank has credits and the operator has none; at 35 tons or more the operator buys its own at 1.15 to 1.
Rentals kept under 12 months (No). California's portable equipment registration (PERP) covers gas engines but isn't valid for supplying a site's primary power. The only exceptions are utility outages, maintenance, a failed backup generator (up to 180 days), and electrical-upgrade work (90 days, or longer if the district agrees in writing). Source
Bay Area Air Quality Management District (BAAQMD) · BAAQMD Data Centers page (last updated Oct 16, 2026) · BAAQMD Regulation 9, Rule 8, Section 9-8-237 (adopted July 25, 2007) · BAAQMD Regulation 2, Rule 2 (New Source Review), Section 2-2-302 (amended Dec 6, 2017) · Checked Nov 8, 2026
High Desert (Mojave Desert AQMD)No ban. Offsets apply once the site's NOx potential reaches 25 tons a year (about 12 MW of gas 24/7, our estimate). Only with a months-long air permit
Permitted plant: Possible (Offsets from 25 tons NOx/yr site-wide)Rentals under 12 months, no air permit: No
Rule 1303(B)(1) requires any new or modified facility with a potential to emit of 25 tpy or more of NOx to obtain offsets; BACT applies per unit at 25 lb/day (Rule 1303(A)(1)).
Also applies here: California, which sets this place's answer together with this rule.
Permitted gas generation (Possible: Offsets from 25 tons NOx/yr site-wide). A new prime gas engine needs a district permit with BACT (25 lb/day per unit) and offsets once the site's NOx potential reaches 25 tons a year (about 12 MW of gas running 24/7 on an otherwise clean site, our estimate).
Rentals kept under 12 months (No). California's portable registration can't supply a site's primary power, so rented units need a district permit like any prime engine. Source
Mojave Desert Air Quality Management District (MDAQMD) · MDAQMD Rule 1303, NSR Requirements (amended 03/25/24), (B)(1) · Checked Nov 8, 2026
Imperial CountyNo air-district ban. Offsets apply once the site's NOx potential reaches 137 lb a day (about 25 tons a year; about 12 MW of gas 24/7, our estimate). Only with a months-long air permit
Permitted plant: Possible (Offsets from 137 lb NOx/day site-wide)Rentals under 12 months, no air permit: No
Rule 207 C.2.a requires offsets for any new or modified stationary source with a daily potential to emit of 137 lb/day or more of NOx; C.2.b requires offsetting all increases that push the source past 137 lb/day.
Also applies here: California, which sets this place's answer together with this rule.
Permitted gas generation (Possible: Offsets from 137 lb NOx/day site-wide). A new prime gas engine needs a district permit with BACT (25 lb/day per unit trigger) and offsets once the site's NOx potential reaches 137 lb a day (about 12 MW of gas running 24/7 on an otherwise clean site, our estimate).
Rentals kept under 12 months (No). California's portable registration can't supply a site's primary power, so rented units need a district permit like any prime engine. Source
Imperial County Air Pollution Control District (ICAPCD) · ICAPCD Rule 207, New and Modified Stationary Source Review (revised 9/11/2018), C.2.a · Checked Nov 8, 2026
Los Angeles / Orange / Riverside / San Bernardino (South Coast AQMD)No ban, but a new prime gas engine must meet 11 ppm NOx, and the whole site owes offsets from 4 tons of NOx a year (about 2 MW of gas running 24/7 on an otherwise clean site, our estimate). Rented portable generators can't power a building except in outages, repairs or remote off-grid work. Only with a months-long air permit
Permitted plant: Possible (Offsets from 4 tons NOx/yr site-wide)Rentals under 12 months, no air permit: No
South Coast does not ban on-site gas at data centers. A non-emergency stationary engine must meet 11 ppmvd NOx (Rule 1110.2 Table II). Under Rule 1304(d), a new or modified facility with a potential to emit of 4 tons a year or more of NOx (or VOC, SOx, PM10) must offset its emission increase under Rule 1303(b)(2), using emission reduction credits at 1.2 to 1. Separately, Rule 1110.2(d)(2)(A) bars any portable engine generator from supplying primary or supplemental power to a facility except during unforeseen utility interruptions, maintenance and repair, and remote operations where grid power is unavailable, unless it meets the stationary-engine limits.
Also applies here: California, which sets this place's answer together with this rule.
Permitted gas generation (Possible: Offsets from 4 tons NOx/yr site-wide). A new prime gas engine needs a district permit with BACT, 11 ppm NOx, and offsets for the site's full NOx increase once the site's potential to emit reaches 4 tons a year (about 2 MW of gas running 24/7 on an otherwise clean site, our estimate).
Rentals kept under 12 months (No). California's portable registration can't supply a site's primary power, and South Coast's own engine rule also bars rented portable generators from powering a facility except in outages, repairs or remote off-grid work, unless the unit meets stationary-engine limits (Rule 1110.2(d)(2)). Source
South Coast Air Quality Management District (SCAQMD) · SCAQMD Rule 1304, Exemptions (amended Nov 5, 2021), (d)(1) and Table A · SCAQMD Rule 1303, Requirements (amended Dec 6, 2002), (b)(2)(A) · SCAQMD Rule 1110.2 (amended Nov 1, 2019), (d)(1)(B) Table II and (d)(2)(A) · Checked Nov 8, 2026
Sacramento CountyNo ban. A prime engine needs a district permit, and the site owes offsets once its NOx potential reaches 5,000 lb a quarter (10 tons a year; about 5 MW of gas 24/7, our estimate). Only with a months-long air permit
Permitted plant: Possible (Offsets from 10 tons NOx/yr site-wide)Rentals under 12 months, no air permit: No
Rule 202 §302.1 requires emission offsets where a regulated pollutant's potential to emit meets or exceeds 5,000 lbs/quarter of NOx. The emergency-equipment exemption (Rule 202 §110) covers only emergency uses such as power during utility interruptions.
Also applies here: California, which sets this place's answer together with this rule.
Permitted gas generation (Possible: Offsets from 10 tons NOx/yr site-wide). A new prime gas engine needs a district permit with BACT, and the site owes offsets once its NOx potential reaches 5,000 lb a quarter (about 5 MW of gas running 24/7 on an otherwise clean site, our estimate).
Rentals kept under 12 months (No). California's portable registration can't supply a site's primary power, so rented units need a district permit like any prime engine. Source
Sacramento Metropolitan Air Quality Management District (SMAQMD) · SMAQMD Rule 202, New Source Review (amended Aug 23, 2012), §302.1 · Checked Nov 8, 2026
San Diego CountyNo ban. Offsets apply once the site's NOx potential reaches 25 tons a year (federal major source in a Severe ozone area), at 1.3 to 1: about 12 MW of gas 24/7 on an otherwise clean site (our estimate). Only with a months-long air permit
Permitted plant: Possible (Offsets from 25 tons NOx/yr site-wide)Rentals under 12 months, no air permit: No
Rule 20.3(d)(5) requires offsets for an emissions increase that constitutes a new major stationary source, new federal major stationary source, or major modification for NOx or VOC. Rule 20.1 Table 20.1-5b sets the federal major source NOx level at 25 tpy for a Severe ozone area (50 tpy state major in Table 20.1-6b). Table 20.3-2 sets a 1.3 to 1 offset ratio for Severe.
Also applies here: California, which sets this place's answer together with this rule.
Permitted gas generation (Possible: Offsets from 25 tons NOx/yr site-wide). A new prime gas engine needs a district permit with BACT; offsets apply only once the site's NOx potential reaches 25 tons a year (about 12 MW of gas running 24/7 on an otherwise clean site, our estimate).
Rentals kept under 12 months (No). California's portable registration can't supply a site's primary power, so rented units need a district permit like any prime engine. Source
San Diego County Air Pollution Control District (SDAPCD) · SDAPCD Rule 20.3 (rev. adopted 10/14/21, effective 10/28/22), (d)(5) · SDAPCD Rule 20.1 (rev. adopted 10/14/21, effective 10/28/22), Table 20.1-5b · Checked Nov 8, 2026
San Joaquin ValleyNo ban. An engine run because the grid hasn't failed is not an emergency engine; a prime gas engine must meet 11 ppm NOx, and the site owes offsets once its NOx potential reaches 20,000 lb a year (about 5 MW of gas 24/7, our estimate). Only with a months-long air permit
Permitted plant: Possible (Offsets from 10 tons NOx/yr site-wide)Rentals under 12 months, no air permit: No
Rule 4702 says an engine is not an emergency standby engine if it is used to reduce demand for electrical power when line service has not failed, so a bridge engine is a regular stationary engine subject to Table 2 (11 ppmv NOx for generic rich- and lean-burn spark-ignited engines). Rule 2201 requires offsets when the post-project stationary source potential to emit equals or exceeds 20,000 lb/yr of NOx (Table 4-1).
Also applies here: California, which sets this place's answer together with this rule.
Permitted gas generation (Possible: Offsets from 10 tons NOx/yr site-wide). A bridge engine is a regular stationary engine: district permit, BACT, 11 ppm NOx, and offsets once the site's NOx potential reaches 20,000 lb a year (about 5 MW of gas running 24/7 on an otherwise clean site, our estimate).
Rentals kept under 12 months (No). California's portable registration can't supply a site's primary power, so rented units need a district permit like any prime engine. Source
San Joaquin Valley Unified Air Pollution Control District (SJVAPCD) · SJVAPCD Rule 2201 (amended Apr 20, 2023; in effect Aug 9, 2023), §4.5.3 Table 4-1 · SJVAPCD Rule 4702 (amended Aug 19, 2021), §3.15 and Table 2 · Checked Nov 8, 2026
New Mexico (outside Bernalillo County)Rented engines need a state air permit; New Mexico doesn't exempt units kept under 12 months. Only with a months-long air permit
Permitted plant: Possible (Permit needed, not paused)Rentals under 12 months, no air permit: No
New Mexico's construction permit rule covers temporary and portable sources, and the state's air agency says it can regulate nonroad engines in permits. Unlike Texas and Louisiana, it has no exemption for rented units kept on a site 12 months or less. A new source must file a notice of intent above 10 tons a year of any pollutant, and needs a construction permit above 10 pounds an hour or 25 tons a year of a pollutant with an air quality standard. A 5–50 MW bridge running 24/7 would pass those lines (our estimate). The permit route is open: there is no pause on data center air permits in New Mexico as of Nov 8, 2026. Albuquerque and the rest of Bernalillo County follow a separate local board rule (20.11.41 NMAC), which exempts portable support power equipment used under 12 consecutive months; whether that reaches a data center bridge is unclear.
Permitted gas generation (Possible: Permit needed, not paused). A 24/7 gas plant needs an NMED construction permit above 10 lb/hr or 25 tons a year of a pollutant with an air quality standard (20.2.72.200.A). No pause is in force.
Rentals kept under 12 months (No). New Mexico counts temporary installations and portable sources as stationary sources, and NMED says it can regulate nonroad engines in its permits. So a rented fleet kept under 12 months still needs a notice of intent and, above the thresholds, a construction permit. We read this as closing the permit-free rental route, not as a ban. Source
Next: Jan 1, 2027. Governor-elect Haaland takes office; she supports a moratorium on new large-scale data centers until the state adopts protections.
New Mexico Environment Department, Air Quality Bureau (20.2.72 and 20.2.73 NMAC; permitting guidance of Apr 2, 2014) · 20.2.72 NMAC, Construction Permits · 20.2.73 NMAC, Notice of Intent · NMED permitting guidance on non-road engines (Apr 2, 2014) · Checked Nov 8, 2026
Southwest Washington (Clark, Cowlitz, Lewis, Skamania and Wahkiakum counties)Rented engines kept under 12 months still need a local nonroad engine permit before they're installed. Only with a months-long air permit
Permitted plant: Possible (Permit needed, not paused)Rentals under 12 months, no air permit: No
Washington's state rule lets nonroad engines kept 12 months or less skip new source review, but the Southwest Clean Air Agency has its own rule. It says its nonroad engine permit requirements "apply to all nonroad engines" in its five counties, except listed exemptions such as installations under 500 horsepower in total that aren't tied to a stationary source, and engines that "replace utility power or utility powered equipment on a temporary basis (< 30 days in duration)". A permit "shall be issued by the Agency prior to the installation" of a covered engine. The application must show the engines meet the ambient air quality standards, a SEPA checklist is required, and the agency decides within 60 days of a complete application or starts public notice. A rented gas fleet sized for a 5–50 MW bridge is far above 500 hp, so it needs this permit (our reading). The permit path is open; this is a hurdle, not a ban.
Permitted gas generation (Possible: Permit needed, not paused). A permanent gas plant goes through SWCAA's stationary source review (SWCAA 400-110), which wasn't read for this row. No pause on data center air permits is in force in Washington as of Nov 8, 2026.
Rentals kept under 12 months (No). Nonroad rentals need a SWCAA nonroad engine permit before installation, with an air quality standards demonstration, a SEPA checklist, a 60-day decision clock and annual registration. Short utility-replacement use under 30 days with Tier-certified engines on ultra-low-sulfur fuel is exempt (400-045(3)(j)), which doesn't cover a months-long bridge. Source
Southwest Clean Air Agency, WA (SWCAA 400 General Regulations for Air Pollution Sources, effective March 10, 2025) · SWCAA 400-045, Permit Application for Nonroad Engines · SWCAA 400-046(2)(a), Application Review Process for Nonroad Engines · SWCAA 400-020(1), Applicability · Checked Nov 8, 2026
Texas 3 places3 rentals only
TexasState permits for data center infrastructure are paused. Only rentals, for gaps under 12 months
Permitted plant: No (Permits paused)Rentals under 12 months, no air permit: Likely yes
Texas's environmental agency has paused issuing permits for infrastructure directly supporting data centers until ERCOT completes its data center review. Neither letter names generators; we read air permits for on-site generators as within that scope.
Permitted gas generation (No: Permits paused). Adding gas generation needs a TCEQ standard permit or air permit, and TCEQ has paused permits for infrastructure directly supporting data centers. No end date. The governor-elect has promised her own moratorium on data center approvals until the Legislature passes new laws.
Rentals kept under 12 months (Likely yes). Texas's air agency said in 2001 that it doesn't treat portable nonroad engines kept on a site 12 months or less as stationary sources. We read that to mean they need no Texas air permit, so the freeze doesn't reach them. Fire, electrical and local permits for the units and their fuel still apply. It works only with EPA nonroad-certified units. The largest rental fleets offer them: Aggreko lists its 1.5 MW gas generator as certified for both nonroad and stationary use. Stationary-only units can't be run as nonroad. Replacement units count toward the 12 months, so rentals can't cover a longer gap. Source
Next: Dec 10, 2026. ERCOT is due to file its two data center audit reports. The freeze runs until ERCOT completes its review.
Governor of Texas (Greg Abbott), directive to TCEQ; implemented by TCEQ · Gov. Abbott letter to TCEQ Executive Director Kelly Keel, Sep 21, 2026 · TCEQ response letter to Gov. Abbott (Interim ED Steven Schar), Oct 19, 2026 · ERCOT filing in PUCT Project 59142 (audit schedule) · Checked Nov 8, 2026
Dallas–Fort Worth areaCovered by the freeze today. After it lifts, a 25-ton emissions line, about 10 MW of gas. Only rentals, for gaps under 12 months
Permitted plant: No (Permits paused; capped near 10 MW once the freeze lifts)Rentals under 12 months, no air permit: Likely yes
In these 10 DFW counties, new generation that could emit 25 tons or more of NOx or VOC a year triggers major-source review: emission offsets at 1.3 to 1 and the strictest controls. For gas that's about 10 MW of modern engines running 24/7 (our estimate; roughly 6–18 MW depending on the engine).
Also applies here: Texas, which sets this place's answer together with this rule.
Permitted gas generation (No: Permits paused; capped near 10 MW once the freeze lifts). Today the statewide freeze applies. After it lifts, new gas generation that could emit 25 tons a year of NOx, or 25 tons of VOC, faces major-source review: offsets at 1.3 to 1 and the strictest controls. That's about 10 MW of modern gas engines running 24/7 (our estimate; roughly 6–18 MW depending on the engine).
Rentals kept under 12 months (Likely yes). Texas's air agency said in 2001 that it doesn't treat portable nonroad engines kept on a site 12 months or less as stationary sources. We read that to mean they need no Texas air permit, so the freeze doesn't reach them. Fire, electrical and local permits for the units and their fuel still apply. It works only with EPA nonroad-certified units. The largest rental fleets offer them: Aggreko lists its 1.5 MW gas generator as certified for both nonroad and stationary use. Stationary-only units can't be run as nonroad. Replacement units count toward the 12 months, so rentals can't cover a longer gap. Source
Next: Jul 20, 2027. Attainment deadline under the 2008 ozone standard. A Severe area that misses it is not moved to Extreme. Large sources start paying federal penalty fees. The Extreme permit rules (a 10-ton line and 1.5 to 1 offsets) apply only if the area still hasn't attained three years later, in July 2030, or sooner if Texas misses a progress milestone.
US EPA (designation/classification); TCEQ (nonattainment NSR, 30 TAC 116.12 and 116.150) · TCEQ Air Permit Reviewer Reference Guide APDG 5881, Major NSR Applicability · 30 TAC §116.12, Table I (nonattainment thresholds and offset ratios) · 89 FR 51829 (June 20, 2024) · Checked Nov 8, 2026
Houston areaCovered by the freeze today. After it lifts, a 25-ton emissions line, about 10 MW of gas. Only rentals, for gaps under 12 months
Permitted plant: No (Permits paused; capped near 10 MW once the freeze lifts)Rentals under 12 months, no air permit: Likely yes
In these 8 Houston-area counties, new generation that could emit 25 tons or more of NOx or VOC a year triggers major-source review: emission offsets at 1.3 to 1 and the strictest controls. For gas that's about 10 MW of modern engines running 24/7 (our estimate; roughly 6–18 MW depending on the engine).
Also applies here: Texas, which sets this place's answer together with this rule.
Permitted gas generation (No: Permits paused; capped near 10 MW once the freeze lifts). Today the statewide freeze applies. After it lifts, new gas generation that could emit 25 tons a year of NOx, or 25 tons of VOC, faces major-source review, about 10 MW of modern gas engines running 24/7 (our estimate). Houston's NOx cap-and-trade program (MECT) also covers a site once its engines could emit 10 tons of NOx a year before controls. That's roughly 1 MW of gas engines (our estimate). A new plant gets no free allowances, so it must buy enough each year to cover every ton it emits.
Rentals kept under 12 months (Likely yes). Texas's air agency said in 2001 that it doesn't treat portable nonroad engines kept on a site 12 months or less as stationary sources. We read that to mean they need no Texas air permit, so the freeze doesn't reach them. Fire, electrical and local permits for the units and their fuel still apply. It works only with EPA nonroad-certified units. The largest rental fleets offer them: Aggreko lists its 1.5 MW gas generator as certified for both nonroad and stationary use. Stationary-only units can't be run as nonroad. Replacement units count toward the 12 months, so rentals can't cover a longer gap. Source
Next: Jul 20, 2027. Attainment deadline under the 2008 ozone standard. A Severe area that misses it is not moved to Extreme. Large sources start paying federal penalty fees. The Extreme permit rules (a 10-ton line and 1.5 to 1 offsets) apply only if the area still hasn't attained three years later, in July 2030, or sooner if Texas misses a progress milestone.
US EPA (designation/classification); TCEQ (nonattainment NSR, 30 TAC 116.12 and 116.150) · TCEQ Air Permit Reviewer Reference Guide APDG 5881, Major NSR Applicability · 30 TAC §116.12, Table I (nonattainment thresholds and offset ratios) · 89 FR 51829 (June 20, 2024) · Checked Nov 8, 2026
Denver metro / North Front RangeA 25-ton emissions line, about 10 MW of gas, before major-source review. Gas plant capped near 10–20 MW
Permitted plant: Capped (Capped near 10 MW)Rentals under 12 months, no air permit: Limited
The Denver-Boulder-Greeley-Ft. Collins-Loveland area is Severe nonattainment for the 2008 ozone standard (since Nov 7, 2022) and Serious for the 2015 standard. Under Colorado Regulation 3 Part D, a source in a severe ozone area is major at 25 tons per year of NOx or VOC, and offsets must be at least 1.3 to 1. New gas generation above that line faces nonattainment review with the strictest controls and offsets. For gas, that's about 10 MW of modern engines running 24/7 (our estimate, same basis as the DFW row). Separately, Colorado's state-only non-road engine program can require a permit for large rental fleets (see co-nonroad-engine-permit).
Permitted gas generation (Capped: Capped near 10 MW). New gas generation that could emit 25 tons a year of NOx or VOC faces nonattainment major-source review: offsets at 1.3 to 1 and LAER. About 10 MW of gas engines running 24/7 (our estimate).
Rentals kept under 12 months (Limited). Rentals kept under 12 months are non-road engines in Colorado, but Colorado's own program requires an emission notice for units of 1,200 hp or more running over 4,380 hours a year, and a temporary state permit when estimated emissions reach 100 tpy NOx (40 tpy at an existing major source). See co-nonroad-engine-permit. Source
Next: Jul 20, 2027. Attainment deadline under the 2008 ozone standard for Severe-15 areas designated in 2012 (CAA 181(a); our date arithmetic, same as DFW). A Severe area that misses it is not bumped to Extreme.
US EPA (designation/classification, 40 CFR 81.306); Colorado AQCC Regulation 3 Part D (CDPHE APCD) · 40 CFR 81.306, Colorado 2008 8-hour ozone table (eCFR, as of Nov 1, 2026) · Colorado AQCC Regulation 3 (5 CCR 1001-5), Part D II.A.25.b.(iii), version 07/15/2026 · EPA Green Book, 8-hour ozone (2008) nonattainment areas (current as of Oct 31, 2026) · Checked Nov 8, 2026
Midwest 50-ton ozone areas 6 places6 capped
Allegan (part), Berrien and Muskegon (part) counties, MISerious ozone areas: new generation over 50 tons a year of NOx or VOC needs major-source review. Gas plant capped near 10–20 MW
Permitted plant: Capped (Capped near 20 MW)Rentals under 12 months, no air permit: Unknown
In Berrien County and the lakeshore parts of Allegan and Muskegon counties, new generation that could emit 50 tons or more of NOx or VOC a year triggers major-source review (roughly 20 MW of gas 24/7, our estimate). Not a ban.
Permitted gas generation (Capped: Capped near 20 MW). Below it, an EGLE permit to install; Rule 278 voids per-engine exemptions when the activity exceeds significance levels.
Rentals kept under 12 months (Unknown). Our reading: R 336.1285(2)(g) exempts engines under 10 MMBtu/h each, but R 336.1278(1)(b) voids the exemption when the activity's emissions exceed significance levels, so a 24/7 rental fleet likely needs a permit to install. Source
US EPA (40 CFR 81.323); Michigan EGLE (R 336.2901 et seq., not read) · 40 CFR 81.323 (Michigan), 2015 8-Hour Ozone table · Checked Nov 8, 2026
Chicago metro (IL-IN-WI)Serious ozone area: new generation over 50 tons a year of NOx or VOC needs major-source review. Gas plant capped near 10–20 MW
Permitted plant: Capped (Capped near 20 MW)Rentals under 12 months, no air permit: Unknown
In Cook, DuPage, Kane, Lake, McHenry and Will counties, parts of Grundy and Kendall counties (IL), five townships of Lake County and eight of Porter County (IN), and eastern Kenosha County (WI), new generation that could emit 50 tons or more of NOx or VOC a year triggers major-source review: offsets and the strictest controls. For gas that is roughly 20 MW of modern engines running 24/7 (our estimate; about 12-36 MW). Not a ban.
Permitted gas generation (Capped: Capped near 20 MW). Above 50 tpy NOx/VOC, nonattainment NSR applies (LAER and offsets). Below it, an Illinois EPA construction permit is still required.
Rentals kept under 12 months (Unknown). Our reading: Illinois has no permit exemption for trailer-mounted rental engines of 1,500 bhp or more (35 IAC 201.146(e) covers only vehicles powered by nonroad engines; 201.146(i) covers stationary engines under 1,500 bhp), and 35 IAC 201.170 requires a construction and operating permit for portable units at a site less than a year. IEPA practice not confirmed. Source
Next: Aug 3, 2027. Serious-area attainment date for the 2015 ozone standard (per FR Dec 17, 2024 reclassification; FR text not re-read in this sweep). Missing it can lead to Severe (25 tpy).
US EPA (designation/classification, 40 CFR 81.314, 81.315, 81.350); Illinois EPA (35 Ill. Adm. Code Part 203 nonattainment NSR); IDEM; Wisconsin DNR · 40 CFR 81.314 (Illinois), 2015 8-Hour Ozone table (eCFR, current to Nov 5, 2026) · 40 CFR 81.315 (Indiana) · 40 CFR 81.350 (Wisconsin) · Checked Nov 8, 2026
Madison, Monroe and St. Clair counties, IL (St. Louis area)Serious ozone area: new generation over 50 tons a year of NOx or VOC needs major-source review. Gas plant capped near 10–20 MW
Permitted plant: Capped (Capped near 20 MW)Rentals under 12 months, no air permit: Unknown
In Madison, Monroe and St. Clair counties, new generation that could emit 50 tons or more of NOx or VOC a year triggers major-source review (roughly 20 MW of gas 24/7, our estimate). Not a ban.
Permitted gas generation (Capped: Capped near 20 MW). 35 IAC 203.206 applies.
Rentals kept under 12 months (Unknown). As il-in-wi-chicago-ozone (our reading).
US EPA; Illinois EPA (35 IAC 203.206) · EPA Green Book, 2015 ozone county listing (current Oct 31, 2026) · 35 Ill. Adm. Code 203.206 · 89 FR 101901 (Serious reclassification, effective Jan 16, 2025) · Checked Nov 8, 2026
Milwaukee metro, WISerious ozone area: new generation over 50 tons a year of NOx or VOC needs major-source review. Gas plant capped near 10–20 MW
Permitted plant: Capped (Capped near 20 MW)Rentals under 12 months, no air permit: Unknown
In Milwaukee and Ozaukee counties and the eastern parts of Racine, Washington and Waukesha counties, new generation that could emit 50 tons or more of NOx or VOC a year triggers major-source review. For gas that is roughly 20 MW of modern engines running 24/7 (our estimate). Port Washington (Ozaukee) and, by our reading of the boundary, Mount Pleasant (eastern Racine) are inside. Not a ban.
Permitted gas generation (Capped: Capped near 20 MW). Above 50 tpy, nonattainment NSR. Below it, a DNR construction permit unless an NR 406.04 exemption applies.
Rentals kept under 12 months (Unknown). Our reading: Wis. Stat. 285.01(41) counts a source 'capable of being transported to a different location' as a stationary source, so a construction permit is needed unless NR 406.04 exempts it; but NR 400.02(143) calls construction-site generators 'semistationary sources'. DNR practice not confirmed. Source
Next: Aug 3, 2027. Serious-area attainment date for the 2015 ozone standard (per FR Dec 17, 2024; not re-read).
US EPA (40 CFR 81.350); Wisconsin DNR (nonattainment NSR, ch. NR 408, not read) · 40 CFR 81.350 (Wisconsin), 2015 8-Hour Ozone table · EPA Green Book, 2015 ozone county listing (current Oct 31, 2026) · Clean Air Act 182(c) (42 U.S.C. 7511a(c)) · Checked Nov 8, 2026
Sheboygan County (part), WISerious ozone area: new generation over 50 tons a year of NOx or VOC needs major-source review. Gas plant capped near 10–20 MW
Permitted plant: Capped (Capped near 20 MW)Rentals under 12 months, no air permit: Unknown
In the lakeshore part of Sheboygan County, new generation that could emit 50 tons or more of NOx or VOC a year triggers major-source review (roughly 20 MW of gas 24/7, our estimate). Not a ban.
Permitted gas generation (Capped: Capped near 20 MW). As wi-milwaukee-ozone.
Rentals kept under 12 months (Unknown). As wi-milwaukee-ozone (our reading).
US EPA (40 CFR 81.350); Wisconsin DNR · 40 CFR 81.350 (Wisconsin) · Checked Nov 8, 2026
St. Louis area, MO (St. Louis City, St. Louis, St. Charles and Jefferson counties; part of Franklin)Serious ozone area: new generation over 50 tons a year of NOx or VOC needs major-source review. Gas plant capped near 10–20 MW
Permitted plant: Capped (Capped near 20 MW)Rentals under 12 months, no air permit: Likely yes
In the City of St. Louis and St. Louis, St. Charles and Jefferson counties, and Boles Township in Franklin County, new generation that could emit 50 tons or more of NOx or VOC a year is a major source and triggers nonattainment review with offsets at 1.2:1 (roughly 20 MW of gas run 24/7, our estimate). Not a ban. Missouri exempts temporary and portable sources from the nonattainment section if they apply BACT, and MoDNR treats rented nonroad engines kept 12 months or less as outside construction permitting (Blitz letter, Kansas City).
Permitted gas generation (Capped: Capped near 20 MW). 10 CSR 10-6.020 'Major source' C(I): 'fifty (50) tpy or more in areas classified as serious'; offsets 1.2:1.
Rentals kept under 12 months (Likely yes). We read rentals of 12 months or less as outside this line: 10 CSR 10-6.060 exempts 'Temporary installation and portable sources' from the nonattainment section if they apply BACT, and MoDNR's Apr 15, 2026 letter treats rented engines on site under 12 months as nonroad engines needing no construction permit (our reading; the letter was for Kansas City, not St. Louis). Source
US EPA (40 CFR 81.326); Missouri DNR Air Pollution Control Program (10 CSR 10-6.020, 10 CSR 10-6.060) · 40 CFR 81.326, Missouri 2015 8-hour ozone table · 10 CSR 10-6.020 (Major source definition) · 10 CSR 10-6.060 nonattainment provisions · Checked Nov 8, 2026
Massachusetts (25 MW+)State permits gated on the state's data center framework and a community benefits agreement. Not blocked: a permit is possible
Permitted plant: Possible (After a community benefits agreement)Rentals under 12 months, no air permit: Likely yes
A new data center over 25 MW, or an expansion adding 25 MW of peak demand, cannot get any state permit (air permits from MassDEP included) until it shows it follows the state's June 2026 data center framework and files a community benefits agreement reviewed by the state environmental justice office. The order does not ban or cap generators.
Permitted gas generation (Possible: After a community benefits agreement). New or expanded data centers over 25 MW can't get any state permit until they show they follow the state's data center framework and file a community benefits agreement. The gas engine itself needs MassDEP self-certification or a plan approval with strict NOx limits.
Rentals kept under 12 months (Likely yes). MassDEP's engine rule (310 CMR 7.26(40)-(45)) does not apply to engines operated as nonroad engines, and its definition of a stationary engine excludes them. Plan approval thresholds don't count combustion emissions, so no plan approval should be needed either (our reading). Fire, electrical and local permits still apply. The largest rental fleets offer EPA nonroad-certified units: Aggreko lists its 1.5 MW gas generator as certified for both nonroad and stationary use. Units certified only as stationary engines likely can't be used this way, because nonroad engines must carry an EPA nonroad certificate (our reading of 40 CFR 1068.101). Replacement units count toward the 12 months. After 12 months at one site, the units become stationary engines and must meet the full engine rule. Source
Next: Dec 31, 2026. MassDEP acts on an alternative compliance payment for data centers that don't buy enough new clean power
Governor Maura Healey, Executive Order 658 (Mass Register No. 1583) · Executive Order No. 658 (mass.gov) · Statement of Expectations for Responsible Data Center Development and Operations (June 25, 2026), Sec. 3 Local Air Quality · Beveridge & Diamond: Massachusetts conditions large data center permits on community agreements · Checked Nov 8, 2026
No places match these filters.
Through 2027, more places are moving to block gas than to allow it.
Marana, AZ Tighter
Ordinance 2026.018 takes effect. Generators at data centers may then run only for genuine, unforeseen outages, testing and commissioning, not because utility power is unavailable or short. A declared state of emergency is still allowed.
Likelihood: High (adopted Oct 20) · Marana Ordinance 2026.018
Upper Allen Township, PA Tighter
Public hearing on a data center and battery storage zoning amendment. Cumberland County's review says the draft prohibits on-site power generation.
Likelihood: Medium · Cumberland County planning review of the draft
Memphis, TN Tighter
About 45 days after the Oct 20 vote, the planning department is due to report data center zoning standards during a 135-day pause on new applications. A pending draft would bar fossil generators as a data center's routine primary power.
Likelihood: Medium · Memphis draft data center regulation (2026 v1)
San José, CA Tighter
City Council first reading of standards for data centers of 20 MW or more (Planning Commission Nov 18; second reading Dec 15; effective about 30 days later). As drafted, backup generators could run only during power outages, which would bar a gas bridge (our reading).
Likelihood: Medium–high · City of San José news release, Oct 9, 2026
Texas Looser
ERCOT is due to file its two data center audit reports, and the PUC takes them up Dec 17. The freeze runs until ERCOT completes its review, so Abbott could lift it before he leaves office.
Likelihood: Low–medium · ERCOT filing in PUCT Project 59142
Dallas–Fort Worth, Houston Looser
EPA says it plans to propose by year-end to reconsider Texas's ozone classifications, and to finish in 2027. It hasn't said what it will propose. If it undoes the 2022 Severe classification, the line would move from 25 to at least 50 tons a year (our reading), about doubling the room for gas.
Likelihood: Medium · EPA release, Sep 29, 2026
New York Tighter
S10642 passed both houses but has not been sent to the Governor. It dies if not sent by Dec 31. Once sent, she has 10 days (Sundays excepted) to act, or it becomes law without her signature.
Likelihood: Low · S10642 / A11560 status
New Mexico Tighter
Governor-elect Haaland takes office. Her campaign says she supports a moratorium on new large-scale data centers until the state adopts protections; press reports she said she'd act by executive order.
Likelihood: High · Haaland campaign release, Sep 18, 2026
Georgia Tighter
Legislature convenes. Bottoms is installed as governor during this session. She has said she will sign an order pausing new data center construction. Unclear whether it reaches air permits.
Likelihood: High (order); medium (air permits) · Bottoms campaign release, Sep 29, 2026
Illinois Tighter
Last days of the old General Assembly (the new one is seated Jan 13). Lawmakers may take up the POWER Act (HB 5513 / SB 4016). As filed, hyperscale data centers would get firm grid service only for load backed by new clean capacity they bring. The rest could be curtailed. On-site gas wouldn't count as clean capacity, though the bill doesn't ban it.
Likelihood: Medium · HB 5513 status (ILGA)
Virginia Tighter
Session opens. The Governor plans a bill to limit on-site gas at data centers. SB 843 would bar every state permit or approval for siting or building a data center, on-site generation included, and all local final approvals, from July 1, 2027 to July 1, 2030.
Likelihood: Medium (gas limits); low (SB 843) · SB 843 (2027), introduced text
Oregon Tighter
Legislature's regular session opens. The Governor says she will introduce a data center bill, which press reports would set standards for where data centers get their power. A new law could end the pause early.
Likelihood: Medium–high · ORS 171.010 (session start)
Texas Tighter
Governor-elect Hinojosa takes office and has promised a moratorium on all data center approvals until the Legislature acts. It likely wouldn't reach rentals that need no permit.
Likelihood: High · Hinojosa campaign, data centers
5 more dates through January 2028
Texas Looser
Regular session must end by May 31. A new data center law could end the moratorium. Most laws take effect 90 days after adjournment unless two-thirds of each house votes for an earlier date.
Likelihood: Medium · Texas Constitution, Art. 3
Oregon Looser
DEQ's pause ends unless lifted earlier or extended.
Likelihood: Medium · Gov. Kotek letter to DEQ, Oct 9, 2026
Virginia Tighter
Effective date for any 2027 law limiting on-site gas.
Likelihood: Medium · SB 843 (2027), introduced text
New York Tighter
About a year after EO 62; the hold ends only when the state's environmental study is final, likely later.
Likelihood: Medium–high it runs longer · Executive Order No. 62
Dallas–Fort Worth, Houston, NYC area Tighter
EPA must say by this date whether these areas met the 2008 ozone standard by July 20, 2027. Missing it does not move a Severe area to Extreme. Large existing sources start paying a yearly emissions fee. Extreme-area permit rules (a 10-ton line and 1.5:1 offsets) apply three years later, in 2030, unless the area meets the standard first. They can apply sooner if ozone is far above the limit or the state missed a progress milestone.
Likelihood: Low before 2030 (our reading) · Clean Air Act §181(b)
Definitions
- No gas route
- A gas plant is barred or its permits are paused, and rented units are barred or need an air permit too.
- Likely no gas route
- The same, but one side rests on our reading: usually a rule that limits generators to “backup” or “emergency” use without defining those words.
- Only with a months-long air permit
- Rented units need an air permit, so any gas, rented or owned, waits on an air permit that takes months.
- Only rentals, for gaps under 12 months
- A gas plant can’t be permitted now, but rented units kept at one site 12 months or less need no air permit. Each needs an EPA nonroad certificate; fire, electrical and local permits still apply.
- Gas plant capped near 10–20 MW
- A plant is possible under an emissions line, about 10 to 20 MW of gas. Above it: offsets and a major-source permit, which usually takes a year or more (our estimate).
- The two answers behind it
- Open any place to see whether a 24/7 gas plant can be permitted (No, Likely no, Capped or Possible) and whether rented units can skip the air permit.
What changed
Second sweep pass. Added zoning bans in Griffin and Port Wentworth, GA; Amherst County, VA; Blakely, PA; and Pittsfield Township, MI (from Nov 9). Added emergency-only rules, marked Likely no, in Athens-Clarke, Gainesville, Rockdale and Porterdale, GA; York and part of Goochland County, VA; Londonderry Township, PA; and Monticello, MN. Added Florida moratoria that pause generator or expansion approvals at existing data centers (Zephyrhills, Hernando, Levy, Nassau, and Leon at 50 MW+). Added St. Louis Metro East to the 50-ton ozone areas and southwest Washington's permit requirement for rented engines.
Earlier changes
- National sweep against primary texts. Added zoning bans in Monroe County, GA; Groton, CT; Bridgewater, NJ; Dallas Township, PA; Henrico County, VA; and Marana, AZ (from Nov 20). Added emergency-only generator rules, marked Likely no, in Tucson, AZ; Edgefield County, SC; Stafford County, VA; and Forsyth, Columbia, Paulding and Pike counties, GA. Added emissions lines in New Jersey, the Philadelphia area, Denver, Connecticut, and the Chicago, Milwaukee, Sheboygan, west Michigan and St. Louis areas. Added California's statewide bar on rented units as primary power with each air district, and New Mexico's permit requirement for rentals.
- Rechecked every rule, outlook item and FAQ answer against the law itself (ordinances, orders, statutes, eCFR). Birmingham's ban covers data centers of every size, not only those over 30 MW. Severe ozone areas that miss their 2027 deadline are not moved to Extreme; they pay fees, and Extreme rules could follow in 2030. New York's treatment of rented units is unclear. Oregon, Bay Area, Nashville, Massachusetts and outlook wording tightened, and outlook items now link their sources.
- Tracker launched with 11 rules, each checked against its primary source on this date.
- Added what each rule means for a built site adding bridge power, separate from new and expanding sites. Oregon, Nashville and New York's 50 MW hold are unclear for built sites.
- Corrections after a line-by-line audit of every rule and source. Texas: TCEQ's stated scope is infrastructure directly supporting data centers, and rented generators kept under 12 months appear to need no permit. Caps: a site's backup generators don't use up its room unless it is already a major source. New York's hold applies at 50 MW or more. Bay Area covers only part of Solano and Sonoma counties.
- Refocused on one question: where data centers can't run on-site gas generation. Each place now answers two things: can you get a permit for 24/7 gas, and can rented gas units kept under 12 months skip it. Rented gas units qualify only with an EPA nonroad certificate; the largest rental fleets offer certified units, so in Texas and Massachusetts a rental under 12 months likely needs no permit. Gas under a 25-ton line revised to about 10 MW.
- Added Birmingham, AL and Coweta County, GA, where zoning bars routine or primary on-site generation at data centers. Added a dated outlook through 2027. Oregon and New York rentals need a state permit.
Common questions
Do batteries need an air permit?
No. A battery doesn’t burn fuel, so there’s nothing for an air agency to permit. The Bay Area air district says so directly: batteries and other zero-emission backup power are exempt from its permits. Batteries do need permits under the local fire code (usually IFC §1207 or NFPA 855) and an electrical permit, and New York City requires an FDNY approval for each battery product.
Why can’t I just run my backup generators while I wait for the utility?
Backup generators are permitted as emergency units. Waiting on a utility connection isn’t an emergency, so running them for that is non-emergency use, and past a small yearly allowance the permit doesn’t cover it. In Texas, according to KERA and the Denton Record-Chronicle, TCEQ issued a notice of enforcement in July 2026 to Core Scientific in Denton for running eight emergency generators for hundreds to more than 1,300 hours each, against a 100-hour limit, while it fixed faulty transformers.
Can I just rent portable gas generators?
In some places, for 12 months or less. A rented portable unit that stays at one site no more than 12 months counts as a nonroad engine under federal rules. To be used that way legally, it needs an EPA nonroad certificate, and at least one of the largest rental fleets (Aggreko) offers certified gas units. Texas and Massachusetts then appear to require no state air permit (our reading), though fire, electrical and local permits still apply. California, New Mexico, Oregon and southwest Washington still require one, and New York’s rules are unclear. New Jersey requires one for units kept over 30 days, unless they count as construction engines, which hasn’t been tested for a running data center. Louisiana, Missouri, North Carolina and Ohio exempt them in their rules or written guidance. In September 2026 New Jersey regulators assessed DataOne a $1.07 million penalty for installing and running 62 gas generators without air permits. Local zoning that bars on-site generation as primary power, as in Nashville, Birmingham and Monroe County, Georgia, covers rented units too (our reading). Replacement units count toward the 12 months, so rentals can’t cover a longer gap.
How much gas generation fits under a 25-ton line?
About 10 MW of modern gas engines running 24/7 (our estimate; roughly 6–18 MW depending on the engine). The estimate assumes the pollutant that binds first, often VOC including formaldehyde, is permitted at about 0.19 g/bhp-hr, with 8,760 hours a year and 1.4 bhp per kW. NOx alone, at 0.05–0.15 g/bhp-hr with SCR, would allow about 12–37 MW. In ozone areas NOx and VOC each have their own 25-ton line. The estimate doesn’t count the site’s existing backup generators.
Do my backup generators use up the room for bridge power?
It depends on whether your site is already a major source. If it isn’t, new generators are judged on their own: a bridge fleet that stays under the line avoids major-source review, even with a large backup fleet on site. If your site is already a major source, which is common for large campuses, the new engines are added to other recent increases at the site, so there may be little room left. Either way, your backup generators’ own permits only allow emergency use and testing, so they can’t serve as the bridge.
How many hours can an emergency generator run?
Federal rules let an emergency generator run without an hour limit during a real emergency, such as a grid outage, plus up to 100 hours a year for maintenance and testing, of which no more than 50 can be other non-emergency use. Many permits allow fewer; the Bay Area allows 50. Running because the utility hasn’t connected you yet is non-emergency use from the first hour.
How often is this updated?
We re-check every rule against its source at least monthly, and sooner when a dated event is coming up. Each entry shows the date we last checked it, and the changelog records every change.
Get the changes
by email.
One short email a month with what changed and what’s coming up. No other mail.
For information only, not legal advice. Confirm with your air agency and fire marshal before you rely on it. Spot an error or a rule we’re missing? Email tyler@relayenergy.us.