Sites of 50 MW or more
DEC permits held for building or expanding data centers of 50 MW+.
Likely no gas route.
Permitted plant: No (DEC permits on hold)Rentals under 12 months, no air permit: Unknown
New York's environmental agency is holding any discretionary permit for building or expanding a data center that uses or can use 50 MW or more, for applications not complete by July 14, 2026, until a statewide environmental study the Governor says will take up to a year. Air permits aren't named; we read them as covered.
Permitted gas generation
The order holds discretionary DEC permits for building or expanding data centers of 50 MW or more, and lets DEC ask whether an application involves a data center's operation. A gas plant for a new or expanding site is likely held. One added at a site that is not growing is arguably outside the hold (our reading).
Rentals kept under 12 months
The rules don't say whether rented units need a state air permit. If they do, a fleet that stays under half the major-source lines can use a registration: 12.5 tons of NOx a year in the NYC area, or 50 tons of NOx and 25 tons of VOC upstate. Registrations are ministerial, so the hold should not reach them. A bigger fleet needs a state facility or Title V permit, which the hold likely catches at 50 MW+ sites being built or expanded. Source
What's next
- Dec 31, 2026. S10642 (A11560) passed both houses in June but has not been sent to the Governor. It dies if not sent before the session ends Dec 31. Once sent, she has 10 days, Sundays excepted, to sign or veto, or it becomes law without her signature.
- Jul 14, 2027. About one year after the order; the hold ends when the environmental study is finished
Details
- Who it covers
- new data centers and expansions of existing ones (applications not deemed complete by Jul 14, 2026)
- Size
- 50 MW or more
- Where
- Statewide, sites of 50 MW or more
- Status
- In force
- Effective
- July 14, 2026
- Authority
- Governor of New York (Kathy Hochul), Executive Order No. 62; implemented by NYSDEC
- Last checked
- November 8, 2026
Sources
- Executive Order No. 62, 'Establishing a Temporary Moratorium on Data Centers in New York While the State Develops Higher Standards for Data Center Development and Benefits Blueprint to Support Localities', Jul 14, 2026 primary
Until DPS submits its report of the final Generic Environmental Impact Statement and associated findings statement, the Department of Environmental Conservation (DEC) ... is directed to hold in abeyance all applications for any discretionary permit, approval, license, or similar form of permission for the construction or expansion of a data center that (1) are or may hereafter be pending before DEC and (2) have not been determined to be complete by DEC before the date of this Executive Order.
- Governor of New York, Executive Orders index primary
No. 62: Establishing a Temporary Moratorium on Data Centers in New York (July 14, 2026); no amending order (62.x) listed as of Nov 8, 2026
- Governor's press release, Sep 15, 2026 (Community Investment Framework) primary
During the development of this GEIS, which will take up to a year from when the Executive Order was issued, a moratorium is in place
For information only, not legal advice. Confirm with your air agency and fire marshal before you rely on it. Spot an error? Email tyler@relayenergy.us.