← Bridge Power Permit Tracker

Sites of 50 MW or more

DEC permits held for building or expanding data centers of 50 MW+.

Likely no gas route.

Permitted plant: No (DEC permits on hold)Rentals under 12 months, no air permit: Unknown

New York's environmental agency is holding any discretionary permit for building or expanding a data center that uses or can use 50 MW or more, for applications not complete by July 14, 2026, until a statewide environmental study the Governor says will take up to a year. Air permits aren't named; we read them as covered.

Permitted gas generation

The order holds discretionary DEC permits for building or expanding data centers of 50 MW or more, and lets DEC ask whether an application involves a data center's operation. A gas plant for a new or expanding site is likely held. One added at a site that is not growing is arguably outside the hold (our reading).

Rentals kept under 12 months

The rules don't say whether rented units need a state air permit. If they do, a fleet that stays under half the major-source lines can use a registration: 12.5 tons of NOx a year in the NYC area, or 50 tons of NOx and 25 tons of VOC upstate. Registrations are ministerial, so the hold should not reach them. A bigger fleet needs a state facility or Title V permit, which the hold likely catches at 50 MW+ sites being built or expanded. Source

What's next

Details

Who it covers
new data centers and expansions of existing ones (applications not deemed complete by Jul 14, 2026)
Size
50 MW or more
Where
Statewide, sites of 50 MW or more
Status
In force
Effective
July 14, 2026
Authority
Governor of New York (Kathy Hochul), Executive Order No. 62; implemented by NYSDEC
Last checked
November 8, 2026

Sources

Check another site Need power here? Talk to us

For information only, not legal advice. Confirm with your air agency and fire marshal before you rely on it. Spot an error? Email tyler@relayenergy.us.