← Bridge Power Permit Tracker

Coweta County, GA

Zoning bars primary on-site power generation at data centers.

No gas route.

Permitted plant: No (Zoning ban)Rentals under 12 months, no air permit: No

Coweta County's data center ordinance says: "Notwithstanding utility grid failure, no primary onsite power generation shall be permitted." Project Sail (Prologis, nine buildings, 4.34 million sq ft, about 900 MW per press) was rezoned on April 7, 2026 under this ordinance and must follow it. The county is rewriting the ordinance under a moratorium on new applications through Dec 13, 2026.

Permitted gas generation

No primary on-site generation. Generators are backup only and must be stationary-source, Tier 4 final units. The rule allows generation only for grid failure, which we read as not covering a wait for a new grid connection.

Rentals kept under 12 months

The rule bars any primary on-site generation and doesn't distinguish owned from rented units. The county administrator said in July 2026 that mobile generators aren't banned as such, but any generator must meet the ordinance (backup only, Tier 4 final). Source

What's next

Details

Who it covers
new data center approvals
Where
Unincorporated Coweta County only
Status
In force
Effective
December 16, 2025
Authority
Coweta County, GA (Board of Commissioners, Dec 2025)
Last checked
November 8, 2026

Sources

Check another site Need power here? Talk to us

For information only, not legal advice. Confirm with your air agency and fire marshal before you rely on it. Spot an error? Email tyler@relayenergy.us.