Coweta County, GA
Zoning bars primary on-site power generation at data centers.
No gas route.
Permitted plant: No (Zoning ban)Rentals under 12 months, no air permit: No
Coweta County's data center ordinance says: "Notwithstanding utility grid failure, no primary onsite power generation shall be permitted." Project Sail (Prologis, nine buildings, 4.34 million sq ft, about 900 MW per press) was rezoned on April 7, 2026 under this ordinance and must follow it. The county is rewriting the ordinance under a moratorium on new applications through Dec 13, 2026.
Permitted gas generation
No primary on-site generation. Generators are backup only and must be stationary-source, Tier 4 final units. The rule allows generation only for grid failure, which we read as not covering a wait for a new grid connection.
Rentals kept under 12 months
The rule bars any primary on-site generation and doesn't distinguish owned from rented units. The county administrator said in July 2026 that mobile generators aren't banned as such, but any generator must meet the ordinance (backup only, Tier 4 final). Source
What's next
- Dec 13, 2026. Moratorium on new data center applications ends; the ordinance is being rewritten. An Aug 2026 staff draft would have allowed on-site generation in the M district. On Oct 13 the Board told staff to drop it and keep the ban. Not adopted yet.
Details
- Who it covers
- new data center approvals
- Where
- Unincorporated Coweta County only
- Status
- In force
- Effective
- December 16, 2025
- Authority
- Coweta County, GA (Board of Commissioners, Dec 2025)
- Last checked
- November 8, 2026
Sources
- Coweta County code, data center standards (Municode) primary
- Coweta County code, Sec. 191(12), M district (same power text; Project Sail's zoning) primary
- Coweta Board of Commissioners minutes, April 7, 2026 primary
- Town of Tyrone data center ordinance audit secondary
- Fox 5 Atlanta on Project Sail secondary
For information only, not legal advice. Confirm with your air agency and fire marshal before you rely on it. Spot an error? Email tyler@relayenergy.us.