Nassau County, FL

Pauses all county approvals for building, expanding or operating data centers, generators included.

Likely no gas route.

Permitted plant: No (Moratorium to about Jun 8, 2027)Rentals under 12 months, no air permit: Unknown

Nassau County paused the acceptance, review or approval of rezonings, conditional uses, development permits, site plans, building permits and other development approvals "for the construction, expansion, or operation of Data Center Facilities" in unincorporated areas, for 12 months or until new rules take effect. The definition says such facilities "may include air handlers, power generators". A county permit for a generator at a data center is therefore paused (our reading).

Permitted gas generation

County approvals for data center construction, expansion or operation are paused. It pauses new data centers too, and likely battery additions at existing ones (our reading).

Rentals kept under 12 months

Rented units need no state air permit, but a county building or site permit for them at a data center would be paused (our reading).

What's next

Details

Who it covers
new and existing data centers in unincorporated Nassau County
Where
Unincorporated Nassau County only
Status
In force
Effective
June 8, 2026
Ends
June 8, 2027
Authority
Nassau County Board of County Commissioners, FL (reported adopted June 8, 2026)
Last checked
November 8, 2026

Sources

Check another site Need power here? Talk to us

For information only, not legal advice. Confirm with your air agency and fire marshal before you rely on it. Spot an error? Email tyler@relayenergy.us.