Nassau County, FL
Pauses all county approvals for building, expanding or operating data centers, generators included.
Likely no gas route.
Permitted plant: No (Moratorium to about Jun 8, 2027)Rentals under 12 months, no air permit: Unknown
Nassau County paused the acceptance, review or approval of rezonings, conditional uses, development permits, site plans, building permits and other development approvals "for the construction, expansion, or operation of Data Center Facilities" in unincorporated areas, for 12 months or until new rules take effect. The definition says such facilities "may include air handlers, power generators". A county permit for a generator at a data center is therefore paused (our reading).
Permitted gas generation
County approvals for data center construction, expansion or operation are paused. It pauses new data centers too, and likely battery additions at existing ones (our reading).
Rentals kept under 12 months
Rented units need no state air permit, but a county building or site permit for them at a data center would be paused (our reading).
What's next
- Jun 8, 2027. Moratorium ends 12 months after it took effect (approximate; it takes effect on filing with the Secretary of State), unless new rules take effect first
Details
- Who it covers
- new and existing data centers in unincorporated Nassau County
- Where
- Unincorporated Nassau County only
- Status
- In force
- Effective
- June 8, 2026
- Ends
- June 8, 2027
- Authority
- Nassau County Board of County Commissioners, FL (reported adopted June 8, 2026)
- Last checked
- November 8, 2026
Sources
- Nassau County, Data Centers page primary
- Ordinance 2026-044, first-reading draft primary
for the construction, expansion, or operation of Data Center Facilities within the unincorporated areas of Nassau County.
- News4Jax, June 9, 2026 secondary
For information only, not legal advice. Confirm with your air agency and fire marshal before you rely on it. Spot an error? Email tyler@relayenergy.us.