Massachusetts (25 MW+)
State permits gated on the state's data center framework and a community benefits agreement.
Not blocked: a permit is possible.
Permitted plant: Possible (After a community benefits agreement)Rentals under 12 months, no air permit: Likely yes
A new data center over 25 MW, or an expansion adding 25 MW of peak demand, cannot get any state permit (air permits from MassDEP included) until it shows it follows the state's June 2026 data center framework and files a community benefits agreement reviewed by the state environmental justice office. The order does not ban or cap generators.
Permitted gas generation
New or expanded data centers over 25 MW can't get any state permit until they show they follow the state's data center framework and file a community benefits agreement. The gas engine itself needs MassDEP self-certification or a plan approval with strict NOx limits.
Rentals kept under 12 months
MassDEP's engine rule (310 CMR 7.26(40)-(45)) does not apply to engines operated as nonroad engines, and its definition of a stationary engine excludes them. Plan approval thresholds don't count combustion emissions, so no plan approval should be needed either (our reading). Fire, electrical and local permits still apply. The largest rental fleets offer EPA nonroad-certified units: Aggreko lists its 1.5 MW gas generator as certified for both nonroad and stationary use. Units certified only as stationary engines likely can't be used this way, because nonroad engines must carry an EPA nonroad certificate (our reading of 40 CFR 1068.101). Replacement units count toward the 12 months. After 12 months at one site, the units become stationary engines and must meet the full engine rule. Source
What's next
- Dec 31, 2026. MassDEP acts on an alternative compliance payment for data centers that don't buy enough new clean power
Details
- Who it covers
- new data centers over 25 MW peak demand, and expansions adding 25 MW, built or expanded after Sept 8, 2026; existing sites not covered unless they expand by 25 MW (research, medical and state-program sites can get a waiver)
- Size
- over 25 MW
- Where
- Statewide
- Status
- In force
- Effective
- September 8, 2026
- Authority
- Governor Maura Healey, Executive Order 658 (Mass Register No. 1583)
- Last checked
- November 8, 2026
Sources
- Executive Order No. 658 (mass.gov) primary
shall not issue any permits or authorizations associated with any data center project with peak electricity demand exceeding twenty-five megawatts to any data center applicant unless that applicant has: (1) demonstrated conformance with the Statement of Expectations ... and (2) submitted a community benefits agreement
- Statement of Expectations for Responsible Data Center Development and Operations (June 25, 2026), Sec. 3 Local Air Quality primary
Use alternatives to diesel-based backup generation, where technically feasible, including solar and storage, and the use of cleaner alternatives, such as fuel cells.
- Beveridge & Diamond: Massachusetts conditions large data center permits on community agreements secondary
built or expanded
- Conservation Law Foundation: Court orders Markley to pause Lowell data center expansion (Aug 10, 2026) secondary
backup diesel generators that have not yet been installed
For information only, not legal advice. Confirm with your air agency and fire marshal before you rely on it. Spot an error? Email tyler@relayenergy.us.