← Bridge Power Permit Tracker

Allegan (part), Berrien and Muskegon (part) counties, MI

Serious ozone areas: new generation over 50 tons a year of NOx or VOC needs major-source review.

Gas plant capped near 10–20 MW.

Permitted plant: Capped (Capped near 20 MW)Rentals under 12 months, no air permit: Unknown

In Berrien County and the lakeshore parts of Allegan and Muskegon counties, new generation that could emit 50 tons or more of NOx or VOC a year triggers major-source review (roughly 20 MW of gas 24/7, our estimate). Not a ban.

Permitted gas generation

Below it, an EGLE permit to install; Rule 278 voids per-engine exemptions when the activity exceeds significance levels.

Rentals kept under 12 months

Our reading: R 336.1285(2)(g) exempts engines under 10 MMBtu/h each, but R 336.1278(1)(b) voids the exemption when the activity's emissions exceed significance levels, so a 24/7 rental fleet likely needs a permit to install. Source

Details

Who it covers
new and existing
Where
Allegan Co.: Casco, Cheshire, Clyde, Fillmore, Ganges, Heath, Laketown, Lee, Manilus [sic, per eCFR], Overisel, Saugatuck, Valley townships and the cities of Douglas, Holland, Saugatuck; Muskegon Co.: listed lakeshore townships and cities (see 40 CFR 81.323)
Status
In force
Effective
January 16, 2025
Authority
US EPA (40 CFR 81.323); Michigan EGLE (R 336.2901 et seq., not read)
Last checked
November 8, 2026

Sources

Check another site Need power here? Talk to us

For information only, not legal advice. Confirm with your air agency and fire marshal before you rely on it. Spot an error? Email tyler@relayenergy.us.