Edgefield County, SC

Zoning limits every generator at a data center to backup or emergency use.

Likely no gas route.

Permitted plant: Likely no (Emergency-only rule)Rentals under 12 months, no air permit: Likely no

Edgefield County's data center rules, adopted July 7, 2026, say: "Except for generator testing or commissioning activities, generator use is limited to backup/emergency use only." The rule covers "any generators on the property" of a data center of any size. Data centers, data center campuses and crypto mining centers are allowed only in the county industrial park at Generac Way, Trenton, at least 1,000 feet from homes. Generators must meet Tier 4 standards and may be tested at most 10 hours a month, 9 a.m. to 5 p.m. The ordinance does not say how it treats sites approved before it.

Permitted gas generation

Generators at a data center may run only for backup or emergency, plus testing and commissioning. 'Backup' is not defined; we read it to exclude bridging while waiting for grid service. Whether this bars a bridge while waiting for the grid is our reading; the rule doesn't say.

Rentals kept under 12 months

The limit applies to "any generators on the property", so rented units are covered (our reading). Source

Details

Who it covers
data centers of any size seeking conditional-use approval; existing sites not addressed
Where
Edgefield County, SC (countywide; data centers allowed only in the county industrial park)
Status
In force
Effective
July 7, 2026
Authority
Edgefield County, SC (County Council, July 7, 2026)
Last checked
November 8, 2026

Sources

Check another site Need power here? Talk to us

For information only, not legal advice. Confirm with your air agency and fire marshal before you rely on it. Spot an error? Email tyler@relayenergy.us.