Zephyrhills, FL
Pauses county or city approvals to build or expand data centers, generators included.
Likely no gas route.
Permitted plant: No (Moratorium to Jun 22, 2027)Rentals under 12 months, no air permit: Likely no
Zephyrhills paused for one year, from June 22, 2026, the acceptance, review and issuance of any city approval for the establishment, expansion or intensification of any data center, data center facility, large-scale data center or large load customer facility. 'Expansion or intensification' expressly includes any change that increases generator capacity, battery storage or fuel storage. The data center definition has no size floor.
Permitted gas generation
Local approvals to establish or expand a covered data center are paused. A generator addition needing a local permit is paused (our reading). It expressly pauses added battery storage as well.
Rentals kept under 12 months
Rented units need no Florida air permit, but a local building, electrical or site approval for them at a covered data center would be paused (our reading). Source
What's next
- Jun 22, 2027. Moratorium ends unless extended or replaced by new rules
Details
- Who it covers
- new and existing data centers of any size in city limits; expansions that add generator, battery or fuel capacity are paused; applications filed before June 22, 2026 are not stated as exempt
- Where
- City of Zephyrhills only
- Status
- In force
- Effective
- June 22, 2026
- Ends
- June 22, 2027
- Authority
- City of Zephyrhills, FL (City Council, June 22, 2026)
- Last checked
- November 8, 2026
Sources
For information only, not legal advice. Confirm with your air agency and fire marshal before you rely on it. Spot an error? Email tyler@relayenergy.us.