Dallas Township, PA
Zoning limits on-site generation to utility outages, 30 days in any 90.
No gas route.
Permitted plant: No (Zoning limit)Rentals under 12 months, no air permit: No
Dallas Township's zoning, amended Jul 28, 2026, says a data center's primary power will come from a public utility. On-site generation may run only when that primary source is unavailable, and no on-site generation may continue longer than 30 days in total in any 90-day period. Data centers are allowed only as a conditional use in the I-1 General Industrial District.
Permitted gas generation
Primary power must come from a public utility. On-site generation runs only when that source is unavailable, and no more than 30 days in any 90.
Rentals kept under 12 months
The 30-in-90-day limit applies to any on-site power generation, so rentals are covered (our reading). Source
Details
- Who it covers
- data centers, accessory structures, power substations and campuses approved under the township zoning ordinance
- Where
- Dallas Township only
- Status
- In force
- Effective
- July 28, 2026
- Authority
- Dallas Township Board of Supervisors, Luzerne County, PA (adopted Jul 28, 2026)
- Last checked
- November 8, 2026
Sources
- Dallas Township Ordinance No. 3 of 2026, final proposed text dated Jul 20, 2026, Section G.1 primary
Primary power will be from a public utility. ... In the interest of public safety, onsite power generation will be limited to use when the primary source is not available. No onsite power generation can continue longer than 30 days in total during any 90-day period.
- Dallas Township special meeting minutes, Jul 28, 2026 (scanned) primary
Motion to Approve the Amendment to the Dallas Township Zoning Ordinance 2026-3 Pertaining to Data Canters, seconded by Supervisor Wagner and carried.
- Times Leader, Jul 28, 2026 secondary
For information only, not legal advice. Confirm with your air agency and fire marshal before you rely on it. Spot an error? Email tyler@relayenergy.us.