Marana, AZ
Zoning limits data center generators to backup use and, from Nov 20, 2026, defines backup to exclude running while utility power is unavailable.
No gas route.
Permitted plant: No (Zoning ban from Nov 20, 2026)Rentals under 12 months, no air permit: No
Marana's data center code (Town Code 17-6-13) already says: "Except for generator testing or commissioning activities, generator use is limited to backup/emergency use only." Until now it did not define backup or emergency. Ordinance 2026.018, adopted Oct 20, 2026 and effective on the 31st day after adoption (Nov 20, 2026), adds a definition "for purposes of this section 17-6-13": backup/emergency use means running generators only during a genuine and unforeseen interruption of the primary supply. It expressly excludes running "as a substitute for, or supplement to, a primary electrical supply that is insufficient, inadequate, unreliable, or unavailable," including when the operator failed to secure utility power, and running for chronic or foreseeable grid shortfalls. It still allows running "during a state of emergency declared by a competent governmental authority." Data centers as a principal use need a specific plan rezoning, and the Council may waive a requirement during that rezoning (17-6-13.C).
Permitted gas generation
Generators may run only for backup/emergency use, testing or commissioning. From Nov 20, 2026, backup expressly excludes running because utility power is unavailable or short, so a bridge plant is barred. A declared state of emergency is still allowed.
Rentals kept under 12 months
The limit is on generator use at the site, so it covers rented units too (our reading; the code doesn't mention rentals). Source
What's next
- Nov 20, 2026. Ordinance 2026.018 takes effect (31st day after Oct 20 adoption). Flip status to in_force and publish then.
Details
- Who it covers
- data centers operated as a principal use under a specific plan; the Council may waive requirements in the rezoning. Whether the new definition binds the Luckett Road specific plan approved in Jan 2026 is not stated (our reading: it governs the code standard that plan was approved under, unless the plan says otherwise)
- Where
- Town of Marana only (Pima County; check whether any town land lies in Pinal County, 04021)
- Status
- Adopted, not yet in force
- Effective
- November 20, 2026
- Authority
- Town of Marana, AZ (Town Council; Ord. 2024.029, Dec 2024; Ord. 2026.018, Oct 20, 2026)
- Last checked
- November 8, 2026
Sources
- Marana Town Code 17-6-13, Table 3 'Generators' (American Legal) primary
Except for generator testing or commissioning activities, generator use is limited to backup/emergency use only. (17-6-13.I, Table 3)
- Marana Ordinance 2026.018 with Exhibit A (adopted Oct 20, 2026) primary
Operation as a substitute for, or supplement to, a primary electrical supply that is insufficient, inadequate, unreliable, or unavailable to meet the data center's power requirements (17-6-13.G.1.b.i, Exhibit A p. 1)
For information only, not legal advice. Confirm with your air agency and fire marshal before you rely on it. Spot an error? Email tyler@relayenergy.us.