Oregon

Air permits for new or expanded data centers paused to July 1, 2027.

No gas route.

Permitted plant: No (Through Jul 1, 2027)Rentals under 12 months, no air permit: No

At the Governor's request (Oct 9, 2026 letter), Oregon DEQ has paused air and water permits for new or expanded data centers until July 1, 2027. DEQ told reporters it will end the pause sooner if the Governor says so, and that it is still working on applications up to a draft permit, then holding them. So no permit for a new or expanded data center can be finalized before then.

Permitted gas generation

Running gas 24/7 at a data center would almost certainly push it past its permitted emission limit, and going past that limit needs a modified DEQ permit. At the Governor's request DEQ has paused permits for new or expanded data centers.

Rentals kept under 12 months

Oregon requires a DEQ air permit for combustion power generation from any unit of 500 kW or more that isn't used only for emergencies, with no exemption for portable or nonroad units. A fleet of smaller units can still need a permit once the site's emissions pass its permit limit or 10 tons a year. For a new or expanded data center, that permit falls under the pause. A small temporary unit inside the site's existing emission limit may avoid a new permit, but DEQ hasn't said whether bridge power qualifies. Source

What's next

Details

Who it covers
new and expanded data centers (existing sites not expanding are not clearly covered)
Where
Statewide
Status
In force
Effective
October 9, 2026
Ends
July 1, 2027
Authority
Governor of Oregon (Tina Kotek), letter to DEQ Director Leah Feldon; implemented by Oregon DEQ
Last checked
November 8, 2026

Sources