← Bridge Power Permit Tracker

Dallas–Fort Worth area

Covered by the freeze today. After it lifts, a 25-ton emissions line, about 10 MW of gas.

Only rentals, for gaps under 12 months. Together with Texas.

Permitted plant: No (Permits paused; capped near 10 MW once the freeze lifts)Rentals under 12 months, no air permit: Likely yes

In these 10 DFW counties, new generation that could emit 25 tons or more of NOx or VOC a year triggers major-source review: emission offsets at 1.3 to 1 and the strictest controls. For gas that's about 10 MW of modern engines running 24/7 (our estimate; roughly 6–18 MW depending on the engine).

Permitted gas generation

Today the statewide freeze applies. After it lifts, new gas generation that could emit 25 tons a year of NOx, or 25 tons of VOC, faces major-source review: offsets at 1.3 to 1 and the strictest controls. That's about 10 MW of modern gas engines running 24/7 (our estimate; roughly 6–18 MW depending on the engine).

Rentals kept under 12 months

Texas's air agency said in 2001 that it doesn't treat portable nonroad engines kept on a site 12 months or less as stationary sources. We read that to mean they need no Texas air permit, so the freeze doesn't reach them. Fire, electrical and local permits for the units and their fuel still apply. It works only with EPA nonroad-certified units. The largest rental fleets offer them: Aggreko lists its 1.5 MW gas generator as certified for both nonroad and stationary use. Stationary-only units can't be run as nonroad. Replacement units count toward the 12 months, so rentals can't cover a longer gap. Source

What's next

Details

Who it covers
new and existing (at a site that isn't yet major, a new project counts on its own; at a major site, it counts with other recent increases)
Where
Collin, Dallas, Denton, Ellis, Johnson, Kaufman, Parker, Rockwall, Tarrant, Wise counties
Status
In force
Effective
November 7, 2022
Authority
US EPA (designation/classification); TCEQ (nonattainment NSR, 30 TAC 116.12 and 116.150)
Last checked
November 8, 2026

Sources

Check another site Need power here? Talk to us

For information only, not legal advice. Confirm with your air agency and fire marshal before you rely on it. Spot an error? Email tyler@relayenergy.us.