Groton, CT
Zoning bans fossil-fuel generation at data centers except during an unforeseen loss of grid power.
No gas route.
Permitted plant: No (Zoning ban)Rentals under 12 months, no air permit: No
Groton's zoning, in force since July 14, 2023, bars on-site power generation using fossil fuels at data centers except during an unforeseen loss of off-site power. Data centers are allowed only by special permit in the IM and IG industrial zones, with server space capped at 12,500 square feet, at least 1,500 feet from another data center, and no evaporative cooling. Accessory data centers (the lesser of 20% of the main use or 1,000 square feet) follow the same standards without a special permit. Waiting for a utility hookup is not an 'unforeseen loss of off-site power' (our reading), so gas or diesel bridge power is barred.
Permitted gas generation
On-site power generation using fossil fuels is barred at data centers except during an unforeseen loss of off-site power. Separately, data centers are limited to 12,500 sq ft of server space and to the IM and IG zones by special permit.
Rentals kept under 12 months
The rule bars 'on-site power generation using fossil fuels' with no exception for rented or temporary units, so rentals are covered too (our reading). Source
Details
- Who it covers
- data centers (server space up to 12,500 sq ft, IM and IG zones, special permit) and accessory data centers, approved under the July 14, 2023 rules; uses lawfully in place before then are not addressed (our reading: they continue as nonconforming uses)
- Where
- Town of Groton only. The City of Groton and Groton Long Point zone separately (our reading).
- Status
- In force
- Effective
- July 14, 2023
- Authority
- Town of Groton, CT Planning and Zoning Commission (REGA23-04, adopted June 27, 2023)
- Last checked
- November 8, 2026
Sources
- Town of Groton Zoning Regulations, Sec. 5.1-6.F Data Center (revised July 15, 2026) primary
Power Generation: On-site power generation using fossil fuels is prohibited except for an occurrence of unforeseen loss of off-site power.
- Groton Planning and Zoning Commission minutes, June 27, 2023 (REGA23-04 approved 5-0, effective July 14, 2023) primary
This text amendment shall become effective July 14, 2023.
- The Day: Groton approves region's first data center regulations secondary
For information only, not legal advice. Confirm with your air agency and fire marshal before you rely on it. Spot an error? Email tyler@relayenergy.us.