St. Louis area, MO (St. Louis City, St. Louis, St. Charles and Jefferson counties; part of Franklin)

Serious ozone area: new generation over 50 tons a year of NOx or VOC needs major-source review.

Gas plant capped near 10–20 MW.

Permitted plant: Capped (Capped near 20 MW)Rentals under 12 months, no air permit: Likely yes

In the City of St. Louis and St. Louis, St. Charles and Jefferson counties, and Boles Township in Franklin County, new generation that could emit 50 tons or more of NOx or VOC a year is a major source and triggers nonattainment review with offsets at 1.2:1 (roughly 20 MW of gas run 24/7, our estimate). Not a ban. Missouri exempts temporary and portable sources from the nonattainment section if they apply BACT, and MoDNR treats rented nonroad engines kept 12 months or less as outside construction permitting (Blitz letter, Kansas City).

Permitted gas generation

10 CSR 10-6.020 'Major source' C(I): 'fifty (50) tpy or more in areas classified as serious'; offsets 1.2:1.

Rentals kept under 12 months

We read rentals of 12 months or less as outside this line: 10 CSR 10-6.060 exempts 'Temporary installation and portable sources' from the nonattainment section if they apply BACT, and MoDNR's Apr 15, 2026 letter treats rented engines on site under 12 months as nonroad engines needing no construction permit (our reading; the letter was for Kansas City, not St. Louis). Source

Details

Who it covers
new and existing
Where
Franklin County: Boles Township only
Status
In force
Effective
December 31, 2024
Authority
US EPA (40 CFR 81.326); Missouri DNR Air Pollution Control Program (10 CSR 10-6.020, 10 CSR 10-6.060)
Last checked
November 8, 2026

Sources